KC-46 Tanker Modernization: Program Cost Is Stable, but Schedule May Be Further Delayed

GAO-18-353 Published: Apr 18, 2018. Publicly Released: Apr 18, 2018.
Jump To:

Fast Facts

Under the Air Force's KC-46 modernization program, commercial aircraft are being converted by Boeing into aerial refueling tankers. The program is one of the Air Force's highest acquisition priorities, and will replace a third of the aging fleet.

We found that the program, now in its seventh year, is meeting its estimated acquisition cost. However, the program office projects that Boeing will not deliver the first 18 fully capable aircraft until May 2019—21 months later than initially planned.

KC-46 Aircraft Refueling a Receiver Aircraft

Photo of a KC-46 aircraft refueling another aircraft.

Photo of a KC-46 aircraft refueling another aircraft.

Skip to Highlights

Highlights

What GAO Found

The total acquisition cost estimate for the KC-46 refueling tanker aircraft remained stable over the last year at $44.4 billion. As shown in the table below, the estimate has decreased about $7.3 billion, or 14 percent, since the initial estimate. This decrease is due in part to stable requirements.

Total Acquisition Cost Estimate for the KC-46 Tanker Aircraft (then-year dollars in millions)

 

February 2011

October 2017

Percent change

Development

7,149.6

5,835.1

-18.4

Procurement

40,236.0

35,523.8

-11.7

Military construction

4,314.6

2,999.8

-30.5

Total

51,700.2

44,358.7

-14.2

Source: GAO presentation of Air Force data. │ GAO-18-353

The program updated its delivery schedule in 2017 to allow Boeing to delay delivery of the first 18 fully capable aircraft from August 2017 to October 2018— 14 months. A schedule risk assessment, as well as GAO's analysis, however projects that deliveries could slip to May 2019, 21 months from the original schedule, if risks are not mitigated. See figure.

Comparison of KC-46 Tanker Original, Updated, and Risk Assessment Schedules

Total Acquisition Cost Estimate for the KC-46 Tanker Aircraft (then-year dollars in millions)

Boeing faces the following risks and challenges and is trying to address them:

updating test aircraft to the correct configuration to complete remaining tests;

completing flight tests at a pace that is almost double its monthly average;

updating test plans to reflect a more realistic schedule for certifying aircraft, such as F-16 fighters and C-17 cargo planes, to be refueled by a KC-46;

retrofitting production aircraft to their final configuration for delivery; and

fixing a critical deficiency to keep the boom from contacting receiver aircraft outside the refueling receptacle.

Because of the terms of the contract, Boeing, not the government, is responsible for nearly $1 billion in additional development costs already incurred. Boeing is also providing additional training for KC-46 pilots, among other things, to compensate the Air Force for delivery delays. Meanwhile, the Air Force is continuing to use KC-135 and KC-10 tankers for refueling missions.

Why GAO Did This Study

The KC-46 tanker modernization program, valued at about $44 billion, is among the Air Force's highest acquisition priorities. Aerial refueling—the transfer of fuel from airborne tankers to combat and airlift forces—is critical to the U.S. military's ability to effectively operate globally. The Air Force initiated the KC-46 program to replace about a third of its aging KC-135 aerial refueling fleet. Boeing was awarded a fixed-price-incentive contract to develop the aircraft. Among other things, Boeing was contractually required to deliver 18 fully capable aircraft (KC-46 aircraft with 9 sets of wing aerial refueling pods that allow for simultaneous refueling of 2 aircraft) by August 2017. The program plans to eventually field 179 aircraft in total.

GAO was asked to monitor the KC-46 program because of problems Boeing is experiencing developing the aircraft. This is GAO's 7th report on the KC-46 program. This report assesses program progress and challenges toward achieving its cost goals and delivery schedule.

GAO analyzed cost, schedule, development, and test information contained in program documents; and discussed results with officials from the KC-46 program office, other defense offices, the Federal Aviation Administration (responsible for certifying the design of the KC-46), and Boeing.

Recommendations

GAO believes the Department of Defense should implement a prior recommendation to document lessons learned given the program's challenges.

Full Report

GAO Contacts

Office of Public Affairs

Topics

Acquisition costsAcquisition programsAir-refueling tankersAircraft acquisition programsContract performanceCost and schedule performanceCost estimatesDelivery termsDevelopmental testingIn-flight refuelingMilitary forcesOperational testingPerformance appraisalPerformance goalsPerformance monitoringPerformance reportingRisk assessmentSchedule slippages