Joint Strike Fighter:
Progress Made and Challenges Remain
GAO-07-360: Published: Mar 15, 2007. Publicly Released: Mar 15, 2007.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Text:
Contact:
(937) 258-7915
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
The Joint Strike Fighter (JSF) program--a multinational acquisition program for the Air Force, Navy, Marine Corps, and eight cooperative international partners--is the Department of Defense's (DOD) most expensive aircraft acquisition program. DOD currently estimates it will spend $623 billion to develop, procure, and operate and support the JSF fleet. The JSF aircraft, which includes a variant design for each of the services, represents 90 percent of the remaining planned investment for DOD's major tactical aircraft programs. In fiscal year 2004, the JSF program was rebaselined to address technical challenges, cost increases, and schedule overruns. This report--the third mandated by Congress--describes the program's progress in meeting cost, schedule, and performance goals since rebaselining and identifies various challenges the program will likely face in meeting these goals in the future.
The JSF program has delivered and flown the first development aircraft. However, cost and schedule goals established in the fiscal year 2004 rebaselined program have not been met. Total JSF program acquisition costs (through 2027) have increased by $31.6 billion and now DOD will pay 12 percent more per aircraft than expected in 2004. The program has also experienced delays in several key events, including the start of the flight test program, delivery of the first production representative development aircraft, and testing of critical missions systems. Delays in the delivery of initial development aircraft were driven by incomplete engineering drawings, changes in design, manufacturing inefficiencies, and parts shortages. Despite these delays, the program still plans to complete development in 2013, compressing the amount of time available for flight testing and development activities. Also, the program projects it will meet all but one key performance requirement--line of sight communications--that is currently dependent on other capabilities being developed outside the JSF program. Accurately predicting JSF costs and schedule and ensuring sufficient funding will likely be key challenges facing the program in the future. JSF continues to pursue a risky acquisition strategy that concurrently develops and produces aircraft. While some concurrency may be beneficial to efficiently transition from development to production, the degree of overlap is significant on this program. Any changes in design and manufacturing that require modifications to delivered aircraft or to tooling and manufacturing processes would result in increased costs and delays in getting capabilities to the warfighter. Low-rate initial production will begin this year with almost the entire 7-year flight test program remaining to confirm the aircraft design. Confidence that investment decisions will deliver expected capability within cost and schedule goals increases as testing proves the JSF will work as expected. The JSF program also faces funding uncertainties as it will demand unprecedented funding over the next 2 decades--more than $12.6 billion a year on average through 2027.
Recommendation for Executive Action
Status: Closed - Implemented
Comments: DOD restructured the JSF program in March 2010. Because of cost increases, continuing delays in manufacturing and testing aircraft, and attendant risks, one of the major decisions was to reduce low rate procurement quantities by 122 aircraft over the next 5 years. We believe DOD's actions to slow the program's production ramp rate by reducing the number of aircraft it plans to buy over the next five years is in line with the intent of our recommendation of reducing the risks of making production commitments prior to demonstrating through flight testing that the aircraft works as intended. While DOD is buying 30 aircraft in fiscal year 2010, by the end of year the program will have tested the basic flying qualities of all three variants. The production risks in subsequent years has been reduced by DOD's actions as the program now plans more time to complete testing before it significantly increasing its production rate. This should improve the program's chances for a successful outcome.
Recommendation: To improve chances of a successful outcome, the Secretary of Defense should limit annual low-rate initial production quantities to no more than 24 aircraft per year, the current manufacturing capacity, until each variant's basic flying qualities have been demonstrated in flight testing now scheduled in the 2010 time frame.
Agency Affected: Department of Defense
Explore the full database of GAO's Open Recommendations
»
Jan 14, 2021
-
Columbia Class Submarine:
Delivery Hinges on Timely and Quality Materials from an Atrophied Supplier BaseGAO-21-257: Published: Jan 14, 2021. Publicly Released: Jan 14, 2021. -
Department of Defense:
Actions Needed to Improve Accounting of Intradepartmental TransactionsGAO-21-84: Published: Jan 14, 2021. Publicly Released: Jan 14, 2021.
Jan 12, 2021
-
DOD Critical Technologies:
Plans for Communicating, Assessing, and Overseeing Protection Efforts Should Be CompletedGAO-21-158: Published: Jan 12, 2021. Publicly Released: Jan 12, 2021.
Dec 10, 2020
-
Climate Resilience:
DOD Coordinates with Communities, but Needs to Assess the Performance of Related Grant ProgramsGAO-21-46: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020. -
Electromagnetic Spectrum Operations:
DOD Needs to Address Governance and Oversight Issues to Help Ensure SuperiorityGAO-21-64: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Dec 2, 2020
-
Navy and Marine Corps:
Services Continue Efforts to Rebuild Readiness, but Recovery Will Take Years and Sustained Management AttentionGAO-21-225T: Published: Dec 2, 2020. Publicly Released: Dec 2, 2020.
Nov 20, 2020
-
GAO Audits Involving DOD:
Status of Efforts to Schedule and Hold Timely Entrance ConferencesGAO-21-185R: Published: Nov 20, 2020. Publicly Released: Nov 20, 2020.
Nov 19, 2020
-
Defense Acquisitions:
Joint Cyber Warfighting Architecture Would Benefit from Defined Goals and GovernanceGAO-21-68: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020. -
Defense Intelligence:
Comprehensive Plan Needed to Improve Stakeholder Engagement in the Development of New Military Intelligence SystemGAO-21-57: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020. -
Defense Production Act:
Opportunities Exist to Increase Transparency and Identify Future Actions to Mitigate Medical Supply Chain Issues:GAO-21-108: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.
Looking for more? Browse all our products here