This is the accessible text file for GAO report number GAO-07-360 
entitled 'Joint Strike Fighter: Progress made and Challenges Remain' 
which was released on March 15, 2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 

GAO: 

March 2007: 

Joint Strike Fighter: 

Progress Made and Challenges Remain: 

GAO-07-360: 

GAO Highlights: 

Highlights of GAO-07-360, a report to congressional committees 

Why GAO Did This Study: 

The Joint Strike Fighter (JSF) program—a multinational acquisition 
program for the Air Force, Navy, Marine Corps, and eight cooperative 
international partners—is the Department of Defense’s (DOD) most 
expensive aircraft acquisition program. DOD currently estimates it will 
spend $623 billion to develop, procure, and operate and support the JSF 
fleet. The JSF aircraft, which includes a variant design for each of 
the services, represents 90 percent of the remaining planned investment 
for DOD’s major tactical aircraft programs. In fiscal year 2004, the 
JSF program was rebaselined to address technical challenges, cost 
increases, and schedule overruns. 

This report—the third mandated by Congress—describes the program’s 
progress in meeting cost, schedule, and performance goals since 
rebaselining and identifies various challenges the program will likely 
face in meeting these goals in the future. 

What GAO Found: 

The JSF program has delivered and flown the first development aircraft. 
However, cost and schedule goals established in the fiscal year 2004 
rebaselined program have not been met. Total JSF program acquisition 
costs (through 2027) have increased by $31.6 billion and now DOD will 
pay 12 percent more per aircraft than expected in 2004. The program has 
also experienced delays in several key events, including the start of 
the flight test program, delivery of the first production 
representative development aircraft, and testing of critical missions 
systems. Delays in the delivery of initial development aircraft were 
driven by incomplete engineering drawings, changes in design, 
manufacturing inefficiencies, and parts shortages. Despite these 
delays, the program still plans to complete development in 2013, 
compressing the amount of time available for flight testing and 
development activities. Also, the program projects it will meet all but 
one key performance requirement—line of sight communications---that is 
currently dependent on other capabilities being developed outside the 
JSF program. 

Accurately predicting JSF costs and schedule and ensuring sufficient 
funding will likely be key challenges facing the program in the future. 
JSF continues to pursue a risky acquisition strategy that concurrently 
develops and produces aircraft. While some concurrency may be 
beneficial to efficiently transition from development to production, 
the degree of overlap is significant on this program. Any changes in 
design and manufacturing that require modifications to delivered 
aircraft or to tooling and manufacturing processes would result in 
increased costs and delays in getting capabilities to the warfighter. 
Low-rate initial production will begin this year with almost the entire 
7-year flight test program remaining to confirm the aircraft design. 
Confidence that investment decisions will deliver expected capability 
within cost and schedule goals increases as testing proves the JSF will 
work as expected. The JSF program also faces funding uncertainties as 
it will demand unprecedented funding over the next 2 decades—more than 
$12.6 billion a year on average through 2027. 

Figure: Overlap of Production Investments and Testing: 

[See PDF for Image] 

Source: DOD data, as of February 2007; GAO analysis and presentation. 

[End of figure] 

What GAO Recommends: 

GAO is recommending that DOD limit annual production quantities to no 
more than 24 aircraft per year until each variant’s basic flying 
qualities have been demonstrated in flight testing now scheduled in the 
2010 time frame. DOD non-concurred, believing its current strategy 
provides a balance of technical risk, financial constraints, and 
operational needs. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-360]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Michael J. Sullivan at 
(202) 512-4841 or sullivanm@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

Program Cost Estimates Have Increased Significantly and Critical 
Milestones Have Been Delayed Since the JSF Was Rebaselined: 

Challenges Remain in Executing the Balance of the JSF Program: 

Conclusions: 

Recommendation for Executive Action: 

Agency Comments and our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Comments from the Department of Defense: 

Tables: 

Table 1: Changes in JSF Program Purchase Quantities and Costs: 

Table 2: JSF Cost Estimate Changes since the Rebaseline: 

Table 3: JSF Program Estimates for Achieving Key Performance 
Parameters: 

Table 4: Comparison between F-22A and Joint Strike Fighter Development 
Programs: 

Figures: 

Figure 1: First JSF Development Aircraft in Flight: 

Figure 2: Changes in JSF Scheduled Events since the Replan: 

Figure 3: Manufacturing Efficiency of First Test Aircraft as of 
November 2006: 

Figure 4: Major Areas of JSF Flight Testing to Be Completed: 

Figure 5: Notional Illustration Showing the Different Paths That JSF 
Development Can Take: 

Figure 6: JSF Program's Annual Funding Requirements: 

Abbreviations: 

CAIG: Cost Analysis and Improvement Group: 
DCMA: Defense Contract Management Agency: 
DOD: Department of Defense: 
JSF: Joint Strike Fighter: 

United States Government Accountability Office: 
Washington, DC 20548: 

March 15, 2007: 

Congressional Committees: 

The Joint Strike Fighter (JSF) is the Department of Defense's (DOD) 
most expensive aircraft acquisition program. The JSF aircraft design 
includes three variants to be used by the Air Force, Navy, Marine 
Corps, and eight cooperative international partners. JSF is a central 
part of DOD's overall recapitalization strategy for its tactical 
aircraft fleet, representing 90 percent of the remaining planned 
investment for its major tactical aircraft programs. DOD currently 
estimates it will spend $276 billion to develop and procure about 2,443 
aircraft and related support equipment by 2027 and an additional $347 
billion to operate and support these aircraft once they have been 
fielded. 

The Ronald W. Reagan National Defense Authorization Act for Fiscal Year 
2005 (P.L. 108-375) requires GAO to review the JSF program annually for 
5 years.[Footnote 1] In the past 2 years, we issued reports identifying 
opportunities for the program to reduce risks and improve the chance 
for more successful outcomes. We recommended DOD pursue an acquisition 
strategy consistent with best practices and DOD policy preferences 
regarding evolutionary and knowledge-based acquisitions including 
deferring production investments until the aircraft have been proven to 
work in flight testing.[Footnote 2] DOD has taken no direct actions in 
response to these recommendations and has stated that its current 
acquisition approach fulfills the intent of DOD policy and further 
limits on production are unnecessary. In 2006 Congress reduced the 
number of production aircraft to be funded in fiscal year 2007 and the 
number of aircraft to receive advanced procurement funds for aircraft 
to be procured in fiscal year 2008. 

This report assesses the progress of the JSF program since it was 
rebaselined in fiscal year 2004 to add resources needed to address 
technical problems. Specifically, we (1) determined the JSF program's 
progress in meeting cost, schedule, and performance goals; and (2) 
identified the challenges and risk the program will face in meeting 
these goals in the future. We performed our work from June of 2006 to 
March of 2007 in accordance with generally accepted government auditing 
standards. For more information on our scope and methodology, see 
appendix I. 

The Act also requires us to certify whether we had access to sufficient 
information to make informed judgments on the matters contained in our 
report. We were provided sufficient information to measure the 
program's progress in meeting its goals based on cost data provided in 
April 2006 as well as the challenges that remain for the program. At 
the time of our review, DOD was still preparing its new cost estimate 
to be included in the program's Selected Acquisition Report dated 
December 31, 2006, expected to be delivered to the Congress by April 
2007. Because the new cost estimate for the JSF program will not be 
available until after this report is issued we are unable to make 
informed judgments on those estimated costs. It should be noted that 
after our 2006 report was issued on March 15, 2006, DOD released its 
December 2005 Selected Acquisition Report, which showed an increase of 
over $19 billion in estimated JSF program costs. 

Results in Brief: 

The JSF program has delivered and flown the first development aircraft 
and has started manufacturing additional development aircraft for the 
test program. JSF program costs have increased by $31.6 billion since 
the program was rebaselined in fiscal year 2004. As a result, DOD will 
pay more per aircraft than was expected when the program was 
rebaselined. The program has also experienced delays in the start of 
the flight test program but has not changed the dates for completing 
development reducing the amount of time available for flight testing 
and development activities. Late design drawings, changes in design and 
manufacturing processes, and late subsystem deliveries caused delays 
that prevented timely manufacturing and delivery of development 
aircraft. The program currently projects that the JSF will meet all but 
one of its key performance requirements--ability to fully interoperate 
with other platforms. These performance projections are based largely 
on engineering analysis, modeling, and laboratory testing and not on 
flight testing. 

The degree of concurrency between development and production in the JSF 
program's acquisition strategy still includes significant risks for 
cost and schedule overruns or late delivery of promised capabilities to 
the warfighter. For example, at the time of the low-rate initial 
production decision, one aircraft will have flown, less than 1 percent 
of the test program will have been completed, and none of the three 
variants will have a production representative prototype built. It will 
not be until about 2012 that a fully capable, integrated JSF is 
scheduled to begin flight testing. A 7-year flight test program that 
includes over 11,000 hours of testing just began in December 2006. 
Therefore, almost all of critical flight testing remains to confirm 
that the aircraft will indeed deliver the required performance. 
Manufacturing and technical problems can delay the completion of a 
flight test program, increase the number of flight test hours needed to 
verify that the system will work as intended, and affect when 
capabilities are delivered to the warfighter. The program also faces 
uncertainties with the amount of funding that will be available to 
support the program's plan. The program will demand unprecedented 
amounts of annual funds over the next 2 decades--more than $12.6 
billion a year on average. Other DOD review and oversight organizations 
have expressed similar concerns over the level of risk in the program 
that will challenge the completion within estimated cost and schedule. 

To improve chances of a successful outcome, we are recommending that 
the Secretary of Defense limit annual production quantities to no more 
than 24 aircraft per year, the current manufacturing capacity, until 
each variant's basic flying qualities have been demonstrated in flight 
testing now scheduled in the 2010 time frame. 

DOD non-concurred with our recommendation stating that the current JSF 
acquisition strategy provides an effective balance of technical risk, 
financial constraints, and operational needs of the services. However, 
we believe DOD's actions to reduce aircraft quantities in the fiscal 
year 2008 President's Budget are in line with our recommendation to 
limit production to current manufacturing capacity until each variant's 
flying qualities have been demonstrated in flight testing. In the 2008 
budget, DOD reduced the number of production aircraft it plans to buy 
during the flight test program by about 35 percent as compared to its 
previous plan for the JSF. Under this new plan DOD does not 
substantially increase its buy quantities of production aircraft until 
2011. We continue to believe that limiting production quantities until 
the design is demonstrated would reduce the overlap in production and 
development while still allowing the efficient transition from 
development to production. It would also make cost and schedule more 
predictable and lessen the risk to DOD's production investment. 

Background: 

JSF is a joint, multinational acquisition program for the Air Force, 
Navy, Marine Corps, and eight cooperative international partners. The 
program began in November 1996 with a 5-year competition between 
Lockheed Martin and Boeing to determine the most capable and affordable 
preliminary aircraft design. Lockheed Martin won the competition, and 
the program entered system development and demonstration in October 
2001. 

The program's objective is to develop and deploy a technically superior 
and affordable fleet of aircraft that support the warfighter in 
performing a wide range of missions in a variety of theaters. The 
single-seat, single-engine aircraft is being designed to be self- 
sufficient or part of a multisystem and multiservice operation, and to 
rapidly transition between air-to-surface and air-to-air missions while 
still airborne. To achieve its mission, JSF will incorporate low 
observable technologies, defensive avionics, advanced onboard and 
offboard sensor fusion, internal and external weapons, and advanced 
prognostic maintenance capability. According to DOD, these technologies 
represent a quantum leap over legacy tactical aircraft capabilities. At 
the same time, the JSF aircraft design includes three variants: a 
conventional take-off and landing variant for the Air Force; an 
aircraft carrier-suitable variant for the Navy; and a short take-off 
and vertical landing variant for the Marine Corps and the United 
Kingdom. JSF is intended to replace a substantial number of aging 
fighter and attack aircraft in DOD's current inventory. 

In 2003 the JSF program system integration efforts and a preliminary 
design review revealed significant airframe weight problems that 
affected the aircraft's ability to meet key performance requirements. 
Software development and integration also posed a significant 
development challenge. The program's inability to meet its ambitious 
goals resulted in the Department's failing to deliver on the business 
case that justified initial investment in JSF. As a result, purchase 
quantities have been reduced, total program costs have increased, and 
delivery of the initial aircraft has been delayed. These changes have 
effectively reduced DOD's buying power for its investment as it will 
now be buying fewer aircraft for a greater financial investment. It is 
too late for the program to meet these initial promises. To its credit, 
in fiscal year 2004, DOD rebaselined the program extending development 
by 18 months and adding resources to address problems discovered during 
systems integration and the preliminary design review. Program 
officials also delayed the critical design reviews, first flights of 
development aircraft, and the low-rate initial production decision to 
allow more time to mitigate design risk and gather more knowledge 
before continuing to make major investments. Table 1 shows the 
evolution of cost and delivery estimates from the start of the program 
up to the latest official program information as of December 2005. 

Table 1: Changes in JSF Program Purchase Quantities and Costs: 

Expected Quantities. 

Development quantities; 
November 1996 (program start): 10; 
October 2001 (system development start): 14; 
December 2003[A](Rebaseline): 14; 
December 2005[A[(Latest available data): 15. 

Procurement quantities (U.S. only); 
November 1996 (program start): 2,978; 
October 2001 (system development start): 2,852; 
December 2003[A](Rebaseline): 2,443; 
December 2005[A](Latest available data): 2,443. 

Total Quantities; 
November 1996 (program start): 2,988; 
October 2001 (system development start): 2,866; 
December 2003[A](Rebaseline): 2,457; 
December 2005[A](Latest available data): 2,458. 

Cost Estimates (Then Year $ in billions). 

Development; 
November 1996 (program start): $24.8; 
October 2001 (system development start): $34.4; 
December 2003[A](Rebaseline): $44.8; 
December 2005[A](Latest available data): $44.5. 

Procurement; 
November 1996 (program start): Not available; 
October 2001 (system development start): 196.6; 
December 2003[A](Rebaseline): 199.8; 
December 2005[A](Latest available data): 231.7. 

Other; 
November 1996 (program start): Not available; 
October 2001 (system development start): 2.0; 
December 2003[A](Rebaseline): 0.2; 
December 2005[A](Latest available data): 0.2. 

Total Program Acquisition; 
November 1996 (program start): Not available; 
October 2001 (system development start): $233.0; 
December 2003[A](Rebaseline): $244.8; 
December 2005[A](Latest available data): $276.5[B]. 

Unit Cost Estimates (Then Year $ in millions). 

Program acquisition; 
November 1996 (program start): Not available; 
October 2001 (system development start): $81; 
December 2003[A](Rebaseline): $100; 
December 2005[A](Latest available data): $112. 

Average procurement; 
November 1996 (program start): Not available; 
October 2001 (system development start): 69; 
December 2003[A](Rebaseline): 82; 
December 2005[A](Latest available data): 95. 

Estimated Delivery Dates. 

First operational aircraft delivery; 
November 1996 (program start): 2007; 
October 2001 (system development start): 2008; 
December 2003[A](Rebaseline): 2009; 
December 2005[A](Latest available data): 2009. 

Initial operational capability; 
November 1996 (program start): 2010; 
October 2001 (system development start): 2010-2012; 
December 2003[A](Rebaseline): 2012-2013; 
December 2005[A](Latest available data): 2012-2015[C]. 

Source: GAO analysis of DOD data. 

[A] The Selected Acquisition Reports are dated December 2003 and 2005 
but are not officially released until March or April of the following 
year. 

[B] Numbers may not add due to rounding. 

[C] Recent program and President's budget information indicates that 
initial operational capability for the Navy's carrier variant has been 
rescheduled from the second quarter of 2013 to the first quarter of 
2015. 

[End of table] 

Program Cost Estimates Have Increased Significantly and Critical 
Milestones Have Been Delayed Since the JSF Was Rebaselined: 

Since establishing a new program baseline in fiscal year 2004, JSF 
program costs have risen and key events have been delayed. JSF program 
costs have increased by $31.6 billion since the program's decision to 
rebaseline in fiscal year 2004. This includes a $19.8 billion increase 
in costs since our report last year in March 2006. The program has 
experienced delays in several key events including delays in the start 
of the flight test program, manufacturing and delivery of the first 
development aircraft, and delays in the testing of critical missions 
systems. These delays reduce the amount of time available for 
completing flight testing and development activities. The program 
projects that it will meet its key performance requirements except for 
one dealing with the warfighter's ability to fully interoperate with 
other platforms. Projections are based largely on engineering analysis, 
modeling, and laboratory testing, and a 7-year test program to 
demonstrate performance just started in December 2006. 

Total Program Cost Estimates Have Increased: 

JSF program cost estimates have increased by $31.6 billion since the 
program's decision to rebaseline in fiscal year 2004. During this 
period, estimates in some cost areas grew by $48 billion but were 
offset by $16.4 billion due to quantity changes and the proposed 
termination of an alternate engine program. According to the program, 
the cost estimate is still mostly based on cost estimating 
relationships--like cost per pound--not actual costs and, therefore, is 
subject to change as the program captures the actual costs to 
manufacture the aircraft. Also, the official program estimate is based 
on the program's December 31, 2005, Selected Acquisition Report 
delivered to Congress in April 2006. We could not review the most 
recent estimated costs of the JSF program. This information is being 
used by the Office of the Secretary of Defense in preparing its fiscal 
year 2008 budget request as well as for the program's Selected 
Acquisition Report dated December 31, 2006, expected to be delivered to 
the Congress in early April 2007. Although the most recent estimates 
were not available for this review, we expect that, unless program 
content is changed, future cost estimates will be higher based on the 
history of similar acquisition programs and the risks that remain in 
the program. Table 2 shows the changes to the program's costs since the 
rebaseline in fiscal year 2004. 

Table 2: JSF Cost Estimate Changes since the Rebaseline: 

(Then-year dollars in billions). 

December 2003 estimated costs; 
Research, development, test and evaluation: $44.8; 
Procurement: $199.8; 
Total: $244.6[A]. 

Cost growth; 
Research, development, test and evaluation: 1.8; 
Procurement: 46.2; 
Total: 48.0. 

Cost reductions; 
Research, development, test and evaluation: (2.1); 
Procurement: (14.3); 
Total: (16.4). 

Elimination of alternate engine program; 
Research, development, test and evaluation: (2.1); 
Procurement: (5.1); 
Total: (7.2). 

Benefits from including partner quantities; 
Research, development, test and evaluation: --; 
Procurement: (9.2); 
Total: (9.2). 

December 2005 estimated costs; 
Research, development, test and evaluation: $44.5; 
Procurement: $231.7; 
Total: $276.2[A]. 

Dollar change; Research, development, test and evaluation: $(0.3); 
Procurement: $31.9; 
Total: $31.6. 

Percent change; 
Research, development, test and evaluation: (0.6); 
Procurement: 16; 
Total: 13. 

Source: GAO analysis of DOD data. 

[A] Does not include estimated military construction costs. 

[End of table] 

Since our last report, the program estimated a $19.8 billion net 
increase in its total program costs. The majority of the cost growth, 
over 95 percent, was for procurement. According to the program office, 
several factors led to an increase in the procurement cost estimate. 
The most significant increases include: 

* $10.3 billion--result of design and manufacturing changes to large 
bulkheads in the wing section of the aircraft, need for 6 times more 
aluminum and almost 4 times more titanium than originally estimated. At 
the same time, titanium costs almost doubled. 

* $3.5 billion--result of reduced manufacturing efficiency because of 
plans to build a certain number of wings at a new subcontractor. 

* $5.5 billion--result of changing the business relationship of the 
prime and two major subcontractors. 

* $4.4 billion--result of projected higher support costs. 

* $14.7 billion--result of changing assumptions for estimating labor 
rates and inflation. 

The increases in procurement costs were offset by two main factors. 
First, the cost estimate reflects production efficiency benefits of 
$9.2 billion from producing 508 international partner aircraft that 
were not included in previous estimates. Secondly, the program reduced 
procurement costs by $5.1 billion as a result of the proposed 
elimination of the alternate engine program. According to the program 
office, it expected savings from manufacturing efficiencies by having 
one engine contractor producing a larger quantity of engines. Program 
officials stated that they have had difficulty quantifying cost savings 
that might accrue from competing engine buys between contractors. For 
now Congress has reinstated the alternate engine program and has 
required further analysis from DOD and others on the costs of the 
program.[Footnote 3] 

The program also reported that development costs decreased by $1.2 
billion. The reduction in development costs was due almost entirely to 
the removal of the remaining estimated costs to complete the alternate 
engine's development. Again, Congress has since reinstated funding for 
the alternate engine program. 

The net effect of the JSF program cost increases is that DOD will pay 
more per aircraft than expected when the program was rebaselined. The 
average procurement unit costs have increased from $82 million to 
almost $95 million and the program acquisition unit costs has increased 
from $100 million to over $112 million. 

Delays in Key Program Events Have Compressed the Development Schedule: 

Since the JSF program was rebaselined, it has experienced delays in 
several key development activities but without corresponding changes to 
the end of development. Holding firm to these dates forces the program 
to find ways to complete development activities in less time, 
especially if problems are discovered in the remaining 6 years of 
development. The program office is evaluating different ways to reduce 
the risk of this compression by being more efficient in its flight test 
activities. The first JSF flight was scheduled for August 2006 but did 
not occur until mid December 2006--about 4 months later than expected. 
According to the program office, the first flight was successful but 
was shortened because of a problem with instrumentation on the 
aircraft. Although the first aircraft will be able to demonstrate some 
performance--limited flying qualities, propulsion, and vehicle 
subsystems--it is not a production representative aircraft with fully 
functioning critical mission systems or the design changes from the 
rebaselined program that reduced airframe weight. 

Figure 1: First JSF Development Aircraft in Flight: 

[See PDF for image] 

Source: JSF program office. 

[End of figure] 

The first flight of a production representative aircraft has been 
delayed 8 months to May 2008. This aircraft will be a short take-off 
and vertical landing variant and will incorporate the design changes 
from the rebaselined program. According to the latest program 
information, the first fully integrated, capable JSF is scheduled to 
begin testing in the early 2012 time frame, a delay of several months. 
The first flight of a JSF with limited mission capability has been 
delayed 9 months. The estimate for first flight of a production 
representative conventional take-off variant has been delayed 11 months 
to January 2009 and the first flight of a carrier variant has been 
delayed by as much as 4 months to May 2009. 

The flying test bed, also critical to reducing risk in the flight test 
program, has been delayed about 14 months to late 2007. This aircraft 
is a modified Boeing 737 that will be equipped with the sensors and 
mission system software and hardware. The test bed will allow the 
program to test aircraft mission systems such as target tracking and 
detection, electronic warfare, and communications. Figure 2 shows 
schedule delays and the compression in the development schedule. 

Figure 2: Changes in JSF Scheduled Events since the Replan: 

[See PDF for image] 

Source: DOD (2007 data); GAO (analysis and presentation). 

[End of figure] 

Design and Manufacturing of Development Aircraft Has Been a Major 
Source of Delay: 

The program has completed manufacturing of its first development 
aircraft and manufacturing data indicates that the program did not meet 
its planned labor hour goals. Manufacturing data on subsequent 
development aircraft that have begun manufacturing indicate these 
aircraft are not currently meeting their planned manufacturing 
efficiencies either. According to contractor data as of November 2006, 
the first development aircraft had required 35 percent or 65,113 more 
labor hours than expected. The program encountered most of the 
inefficiencies in the mate and delivery phase and with the fabrication 
of the center fuselage and wing. Figure 3 shows the planned hours 
versus the actual hours needed for completing the first test aircraft. 

Figure 3: Manufacturing Efficiency of First Test Aircraft as of 
November 2006: 

[See PDF for image] 

Source: Lockheed Martin (data); GAO (analysis). 

[End of figure] 

When the first aircraft began manufacturing, the program had released 
about 20 percent of the engineering drawings needed for building the 
aircraft. This led to a backlog of drawings, negatively impacting the 
availability of parts needed for efficient manufacturing operations. To 
compensate for delays and parts shortages for production, components of 
the aircraft were manufactured out of sequence and at different 
manufacturing workstations than planned. For example, the wing section 
was mated to the center fuselage before work on the wing was completed. 
The wing was only 46 percent complete and still required more than 
18,500 hours of work. Because this remaining work was completed at a 
different workstation than was planned, contractor officials stated 
that major tooling--such as a stand that supports the wing structure 
upright to allow workers to install wiring and other parts--was not 
available for use. As a result, workers were required to lie on the 
ground or bend under or over the wing structure to complete the wing 
assembly, significantly increasing the number of hours needed to 
complete this effort. According to Defense Contract Management Agency, 
out-of-station work performed on the wing required an additional 46 
percent more hours than planned. Late delivery of parts and late 
qualification of subsystems were the major drivers to the mate and 
delivery inefficiencies, more than doubling the hours needed to 
complete this activity. 

Lockheed Martin, the prime contractor, appears to be focused on 
developing an efficient and effective manufacturing process for the 
JSF, but it is still very early in that process. The development 
aircraft now in manufacturing are not currently meeting their planned 
efficiencies. As with the first test aircraft, the program does not 
expect to manufacture the development aircraft in the planned 
manufacturing sequence. The program expects to move some wing 
fabrication activities to final assembly and do both fabrication and 
final assembly concurrently. Early development aircraft are already 
experiencing inefficiencies and delays. As of December 2006, wing 
manufacturing data for one of these aircraft shows the program had 
completed less than 50 percent of the activities expected at this time 
while requiring 41 percent more hours than planned. According to the 
contractor and program officials, these inefficiencies are largely due 
to late delivery of the wing bulkheads because of a change in their 
manufacturing process. The Defense Contract Management Agency has rated 
manufacturing as high risk, stating that the primary cause of risk is 
the late delivery of parts to properly support the manufacturing work 
flow. It projects further delays to schedule, increased costs, and 
subsequent out-of-sequence work. 

An early indicator of design stability is the completion of design 
drawings at the critical design review. In February 2006, the program 
held its critical design review for production representative 
conventional and short take-off and vertical landing aircraft.[Footnote 
4] At that time, the program had completed 47 percent of the short take-
off aircraft design and 3 percent of the conventional aircraft design. 
Our previous best practices work suggests that completion of 90 percent 
of a product's engineering drawings provides tangible evidence that the 
design is stable. As with the first aircraft, the program has 
experienced late releases of engineering drawings, which has delayed 
the delivery of critical parts from suppliers to manufacturing for the 
building of the initial aircraft. For example, based on program data as 
of October 2006, more than one-third of the drawings needed to complete 
these two variants are expected to be released late to manufacturing. 

Although the first aircraft encountered manufacturing inefficiencies, 
the JSF Program and the contractor have pointed to some successes in 
this initial manufacturing effort. For example, they have stated the 
mate of the major sections of the aircraft was more efficient than in 
past aircraft programs because of the state-of-the-art tools used to 
design the aircraft and develop the manufacturing process. Likewise, 
they have indicated that they have experienced fewer defects in this 
first aircraft than experienced on legacy aircraft. 

We would agree that the contractor has made progress in demonstrating 
the use of several large tools and fabrication processes in building 
the first test aircraft. However, a key factor in developing an 
efficient and effective manufacturing process is a mature aircraft 
design. Major design modifications can cause substantial and costly 
changes in the manufacturing process. For example, since the first 
aircraft entered production, the manufacturing process has had to be 
altered due to redesigning required to resolve weight and performance 
problems. According to Defense Contract Management Agency officials, 
some tools already bought and in place were either no longer useful or 
being used less efficiently. New tools had to be procured and the 
manufacturing process had to change. The Defense Contract Management 
Agency noted that these additional tooling costs were about $156 
million. Contractor officials stated that the current manufacturing 
capacity is sufficient to produce about 24 aircraft per year. Given 
that only one aircraft has been built and essentially all of the flight 
and static and durability testing remains to be done there is still 
significant risk that the JSF design for each of the three variants 
will incur more changes as more design knowledge is gained. 

The JSF Program Projects Key Performance Parameters Will Be Met Based 
on Modeling and Simulations: 

Currently, the JSF program estimates that by the time the development 
program ends the aircraft design will meet all but one of its key 
performance parameters. The performance estimates to date are based on 
engineering analyses, computer models, and laboratory tests. Key 
performance parameters are defined as the minimum attributes or 
characteristics considered most essential for an effective military 
capability--for the JSF there are eight parameters. The program office 
estimates that seven of the eight key performance parameters are being 
met. The aircraft is currently not meeting its full interoperability 
performance parameter due to a requirement for beyond-line-of-sight 
communications. Meeting the full interoperability required is currently 
dependent on other capabilities being developed outside the JSF 
program. Most ground and flight tests will have to be completed before 
all the key performance estimates are confirmed. At this time, the 
program has completed less than 1 percent of the flight test program 
and no structural or durability tests have been started. According to 
the program's test and evaluation master plan, the key performance 
parameters will be verified during testing from 2010 to 2013. Table 3 
shows the program's estimate for each key performance parameter. 

Table 3: JSF Program Estimates for Achieving Key Performance 
Parameters: 

Key performance parameter: Combat radius; 
Status: Meeting: Check; 
Status: Not meeting: [Empty]; 
Confirmed through flight testing: Yes: [Empty]; 
Confirmed through flight testing: No: Check. 

Key performance parameter: CV Recovery; 
Status: Meeting: Check; 
Status: Not meeting: [Empty]; 
Confirmed through flight testing: Yes: [Empty]; 
Confirmed through flight testing: No: Check. 

Key performance parameter: STOVL Performance; 
Status: Meeting: Check; 
Status: Not meeting: [Empty]; 
Confirmed through flight testing: Yes: [Empty]; 
Confirmed through flight testing: No: Check. 

Key performance parameter: Interoperability; 
Status: Meeting: [Empty]; 
Status: Not meeting: Check; 
Confirmed through flight testing: Yes: [Empty]; 
Confirmed through flight testing: No: Check. 

Key performance parameter: Radio frequency signature; 
Status: Meeting: Check; 
Status: Not meeting: [Empty]; 
Confirmed through flight testing: Yes: [Empty]; 
Confirmed through flight testing: No: Check. 

Key performance parameter: Mission reliability; 
Status: Meeting: Check; 
Status: Not meeting: [Empty]; 
Confirmed through flight testing: Yes: [Empty]; 
Confirmed through flight testing: No: Check. 

Key performance parameter: Sortie Generation Rate; 
Status: Meeting: Check; 
Status: Not meeting: [Empty]; 
Confirmed through flight testing: Yes: [Empty]; 
Confirmed through flight testing: No: Check. 

Key performance parameter: Logistics footprint; 
Status: Meeting: Check; 
Status: Not meeting: [Empty]; 
Confirmed through flight testing: Yes: [Empty]; 
Confirmed through flight testing: No: Check. 

Source: GAO analysis of JSF program office data. 

[End of table] 

Challenges Remain in Executing the Balance of the JSF Program: 

The JSF program's acquisition strategy includes significant challenges 
to achieve projected cost and schedule goals. The program has begun 
procurement but not yet demonstrated that the aircraft design is 
mature, can be manufactured efficiently, and delivered on time. The 
flight test program has just begun, and there is always risk of 
problems surfacing and causing further delays. The degree of 
concurrency between development and production in the JSF program's 
acquisition strategy still includes significant risks for cost and 
schedule overruns or late delivery of promised capabilities to the 
warfighter. The program also faces uncertainties with the amount of 
funding that will be available to support the program's plan. Other DOD 
review and oversight organizations have also expressed concern over the 
level of risk in the program and the resulting costs that will be 
incurred to complete this acquisition program. 

Challenges to Complete Flight Testing: 

The program has planned a 7-year flight test program that includes over 
11,000 hours of testing and over 6,000 flights. This is 75 percent more 
than the F-22A's flight test program and more than double the F/A-18E/ 
F testing efforts. As of this report, the flight test program was only 
beginning with essentially all critical flight testing remaining to 
confirm that the aircraft will indeed deliver the required performance. 
Figure 4 shows the planned flight tests by major test categories. 

Figure 4: Major Areas of JSF Flight Testing to Be Completed: 

[See PDF for image] 

Source: Lockheed Martin (data); GAO (analysis). 

[End of figure] 

The JSF variants possess significant similarities--all designed to have 
low observable airframe characteristics, fly at supersonic speeds, 
shoot air-to-air missiles, and drop bombs on target--but each variant 
has unique performance goals to support the services' different 
operational concepts and environments. Test officials acknowledge that 
each variant will require separate flight testing to demonstrate that 
it will fly as intended. About two-thirds of the flight tests are 
planned for demonstrating the performance of each aircraft design. The 
other one-third of the flight tests are expected to confirm shipboard 
operations, mission systems, survivability, and armament. 

Manufacturing and technical problems can delay the completion of a 
flight test program, increase the number of flight test hours needed to 
verify that the system will work as intended, and affect scheduled 
delivery to the warfighter. Under the current testing schedule, the JSF 
program plans to manufacture and deliver 15 flight test aircraft and 7 
ground test articles in 5 years--an aggressive schedule when compared 
with other programs with fewer variables. For example, the F-22A 
program took almost 8 years to manufacture and deliver nine flight test 
aircraft and two ground test articles of a single aircraft design. When 
the B-2 program began flight testing in July 1989, it estimated that 
the flight test program would last approximately 4.5 years and require 
about 3,600 flight test hours. When the test program ended in 1997, the 
flight test hours had grown to 5,000 hours, or by 40 percent, over an 8-
year period. Program officials cited several causes, including 
difficulties in manufacturing test aircraft and correcting deficiencies 
from problems discovered during testing. The F-22A encountered similar 
delays increasing a planned 4-year flight test program to about 8 
years, affecting the program's ability to conduct operational testing 
and move into production on schedule. As discussed earlier, current JSF 
schedules are already showing that delivery of early test aircraft will 
be later than the planned delivery date. 

The flight test program will also hinge on the delivering aircraft with 
the expected capabilities. JSF's expected capabilities are largely 
dependent on software that supports vehicle and mission systems. The 
program plans to develop over 22 million lines of code--more than 6 
times the lines of code needed for the F-22A--in five blocks. The first 
block is nearly complete and the last block is scheduled for completion 
in late 2011. The program has completed less than 40 percent of the 
software needed for the system's full functionality. Most of the 
completed software is designed to operate the aircraft's flying 
capabilities, while much of the remaining software development includes 
software needed for mission capability, including weapons integration 
and the fusion of information from onboard sensors and sources off the 
aircraft. Past programs have encountered difficulties in developing 
software, which delayed flight test schedules. JSF program officials 
acknowledged that the software effort will become particularly 
challenging during 2007 and 2008 when all five software blocks will be 
in development at the same time. 

Challenges Created by Continued Concurrent Development and Production: 

The concurrency between development and production in DOD's acquisition 
strategy for JSF did not substantially change as a result of the 
program's rebaseline in fiscal year 2004. Therefore, the program is 
entering low-rate initial production without demonstrating through 
flight testing that (1) the aircraft's flying qualities function within 
the parameters of the flight envelope--that is, the set limits for 
altitude, speed, and angles of attack; (2) the aircraft design is 
reliable; or (3) a fully integrated and capable aircraft system can 
perform as intended. Starting production before ensuring design 
maturity through flight testing significantly increases the risk 
because of the of costly design changes that will push the program over 
budget and behind schedule. Failure to capture key design knowledge 
before producing aircraft in quantity can lead to problems that 
eventually cascade and become magnified through the product development 
and production phases. Figure 5 is a notional illustration showing the 
impacts that can result from a highly concurrent acquisition strategy 
to one with less concurrency and that captures key design and 
manufacturing data before production begins. 

Figure 5: Notional Illustration Showing the Different Paths That JSF 
Development Can Take: 

[See PDF for image] 

Source: GAO. 

[End of figure] 

While some concurrency may be beneficial to efficiently transition from 
the development stage of a program to production, the JSF is currently 
planned to be significantly more concurrent than the F-22A program that 
failed to deliver the warfighting capability on time and at predicted 
costs. Table 4 provides a more detailed comparison between the JSF and 
F-22A development programs and the accomplishments and requirements 
before starting production in each program. 

Table 4: Comparison between F-22A and Joint Strike Fighter Development 
Programs: 

Flight test program accomplished.  

Flight test hours; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: F-22A: Approximately 1,300; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: Joint Strike Fighter: Approximately 30; 
Point When Joint Strike Fighter Will Match Similar F-22A 
Accomplishments: 2008. 

Percent of flight test hours; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: F-22A: 20 percent; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: Joint Strike Fighter: Less than 1 percent; 
Point When Joint Strike Fighter Will Match Similar F-22A 
Accomplishments: 2009. 

Number of flight test aircraft delivered; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: F-22A: 6 of 9; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: Joint Strike Fighter: 1 of 15; 
Point When Joint Strike Fighter Will Match Similar F-22A 
Accomplishments: 2009. 

Months of flight testing; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: F-22A: 48; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: Joint Strike Fighter: 3; 
Point When Joint Strike Fighter Will Match Similar F-22A 
Accomplishments: 2010. 

Key test events accomplished. 

Initiated fatigue testing; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: F-22A: Yes; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: Joint Strike Fighter: No; 
Point When Joint Strike Fighter Will Match Similar F-22A 
Accomplishments: 2008. 

Initiated separation of weapons testing; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: F-22A: Yes; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: Joint Strike Fighter: No; 
Point When Joint Strike Fighter Will Match Similar F-22A 
Accomplishments: 2009. 

Initiated radar cross section testing; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: F-22A: Yes; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: Joint Strike Fighter: No; 
Point When Joint Strike Fighter Will Match Similar F-22A 
Accomplishments: 2009. 

Full scale static testing; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: F-22A: Yes; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: Joint Strike Fighter: No; 
Point When Joint Strike Fighter Will Match Similar F-22A 
Accomplishments: 2009. 

First flight of fully integrated aircraft; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: F-22A: Yes; 
Status of Flight Test Programs at the Start of Low Rate Initial 
Production: Joint Strike Fighter: No; 
Point When Joint Strike Fighter Will Match Similar F-22A 
Accomplishments: 2012. 

Source: GAO analysis of DOD data. 

[End of table] 

As a result of the risk associated with highly concurrent development 
and production, the JSF program plans to place initial production 
orders on cost reimbursement contracts. Cost reimbursement contracts 
provide for payment of allowable incurred costs, to the extent 
prescribed in the contract. Such contracts are used when costs cannot 
be estimated with sufficient accuracy to use any type of fixed price 
contract. Cost reimbursement contracts place a substantial risk on the 
buyer--in this case DOD--because the contractor's responsibility for 
the cost risks of performance has been minimized or reduced. As 
knowledge is gained over time, the program office intended to shift the 
contract type to one where more cost risk is placed on the contractor. 
However, DOD materials supporting the President's fiscal year 2008 
budget show that all low rate production orders will be placed on cost 
reimbursement contracts. 

Unprecedented Funding Requirements Could Challenge Program Execution: 

To execute its current plan, the JSF program must obtain unprecedented 
levels of annual funding--on average over $12.6 billion annually in 
acquisition funds over the next 2 decades. Regardless of likely 
increases in program costs, the sizeable continued investment in JSF-- 
estimated at roughly $252 billion over 20 years--must be viewed within 
the context of the fiscal imbalance facing the nation within the next 
10 years. The JSF program will have to compete with many other large 
defense programs, such as the Army's Future Combat System and the 
Missile Defense Agency's ballistic missile defense system, for funding 
during this same time frame. There are also important competing 
priorities external to DOD's budget. Fully funding specific programs or 
activities will undoubtedly create shortfalls in others. 

Funding challenges will be even greater if the program fails to achieve 
current cost and schedule estimates for the revised program baseline. 
The consequences of an even modest cost increase or schedule delay on a 
program this size is dramatic. For example, since the program 
rebaseline in fiscal year 2004, the estimated annual funding 
requirements have increased every year from 2012 to 2027 by at least $1 
billion and in some cases by $3 to $7 billion. These funding increases 
would be enough to fund several major programs' activities. Figure 6 
shows growth in estimated annual funding requirements from December 
2003 to December 2005. 

Figure 6: JSF Program's Annual Funding Requirements: 

[See PDF for image] 

Source: GAO analysis of DOD data. 

[End of figure] 

Due to affordability pressures, DOD is beginning to reduce procurement 
budgets and annual quantities. The just-released fiscal year 2008 
defense budget shows declining procurement quantities for the first 
years of production. To meet future constrained acquisition budgets, 
Air Force and Navy officials and planning documents suggest a decrease 
in maximum annual buy quantities from 160 shown in the current program 
of record to about 115 per year, a 28 percent decrease. While this will 
reduce annual funding requirements, it will also stretch the 
procurement program at least 7 years to 2034, assuming buy quantities 
are deferred rather than eliminated. 

DOD Organizations Have Raised Concerns about Program Risks and 
Estimated Costs: 

DOD's military service operational test organizations, the Cost 
Analysis and Improvement Group (CAIG), and the Defense Contract 
Management Agency (DCMA) have expressed concerns over the level of risk 
and estimated costs of the program. These oversight and testing 
organizations highlight some of the program risks and the challenges 
the JSF program must overcome to avoid further slips in schedule and 
more cost growth. 

A February 2006 operational assessment of the JSF program by Air Force, 
Navy and United Kingdom operational test officials noted several areas 
of risk. According to the test report, several of these issues, if not 
adequately addressed, are likely to pose substantial or severe 
operational impact to the JSF's mission capabilities. Key concerns 
raised in the report include the following: 

* Software development and testing schedules are success-oriented and 
have little margin to accommodate delays. 

* Developmental flight test schedule provides little capability to 
respond to unforeseen problems and still meet scheduled start of 
operational testing. This threatens to slip operational testing and 
initial operational capability. 

* Predicted maintenance times for propulsion system support, integrated 
combat turn, and gun removal and installation do not meet requirements. 

* Design requirements to preserve volume, power, and cooling for future 
growth are in jeopardy and will limit capability to meet future 
requirements. 

* Certain technical challenges in the aircraft or its subsystem design 
that could impact operational capability. 

In a follow-up discussion on the report, test officials stated that 
these concerns were still current and they had not been informed by the 
program office of planned actions to address them. The December 2006 
Annual Report of DOD's Director, Operational Test and Evaluation 
recommended that the JSF program follow up on these issues. 

The CAIG has expressed concerns about the reality of estimated program 
costs. Its preliminary cost estimate in 2005 was substantially higher 
than the program office estimate. The CAIG cited costs associated with 
mission systems, system test, engines, and commonality as drivers in 
the difference between its estimate and that of the program office. 
According to discussions in 2006 with CAIG officials, they still have 
concerns and continue to expect program costs to be much higher than 
the program office's current estimate. The CAIG is not required to 
submit its next formal independent cost estimate until the preparations 
for Milestone C, which for the JSF program is full-rate production. For 
major defense acquisition programs, this milestone generally should 
occur before low-rate initial production. Milestone C is scheduled for 
late 2013. 

DCMA's concerns focus on the prime contractor's ability to achieve its 
cost and schedule estimates. DCMA, responsible for monitoring the prime 
contractor's development and procurement activities, found that delays 
in aircraft deliveries and critical technical review milestones put at 
risk the contractor's ability to meet the current schedule. DCMA also 
identified manufacturing operations as a high-risk area highlighting 
issues with parts delivery, raw material availability, and 
subcontractor performance. Finally, it raised concerns with contractor 
cost growth stating that the contractor has shown continuing and steady 
increases since development started, even after the contract's target 
price was increased by $6 billion as part of the program's rebaseline. 
As of November 2006, DCMA projects that the contractor's current 
estimated development costs will increase by about $1 billion. 

Conclusions: 

The JSF is entering its 6th year of a 12-year development program and 
is also entering production. The development team has achieved first 
flight and has overcome major design problems found earlier in 
development. In addition, the department counts on this aircraft to 
bear the brunt of its recapitalization plans. Therefore, we believe the 
program is critical to the department's future plans and is viable, 
given progress made to date. However, the current acquisition strategy 
still reflects very significant risk that both development and 
procurement costs will increase and aircraft will take longer to 
deliver to the warfighter than currently planned. Even as the JSF 
program enters the mid point of its development, it continues to 
encounter significant cost overruns and schedule delays because the 
program has continued to move forward into procurement before it has 
knowledge that the aircraft's design and manufacturing processes are 
stable. Although some of the additional costs were predictable, other 
costs, especially those resulting from rework, represent waste the 
Department can ill afford. 

Flight testing began just a few months before the decision to begin low-
rate initial production. The challenges and risks facing the program 
are only expected to increase as the program begins to ramp up its 
production capabilities while completing design integration, software 
design, and testing. DOD's approval to enter low-rate initial 
production this year committed the program to this high risk strategy. 
If the program is unable to mitigate risks, its only options will be to 
reduce program requirements or delay when the program achieves initial 
operational capability. We see two ways this risk can be reduced: (1) 
reducing the number of aircraft for procurement before testing 
demonstrates their performance capabilities, thereby reducing the 
potential for costly changes to the aircraft and manufacturing 
processes or (2) reexamining the required capabilities for initial 
variants with an eye toward bringing them up to higher capability in 
the future. 

Last year Congress reduced funding for the first two low-rate 
production lots of aircraft thereby slowing the ramp up of production. 
This was a positive first step in lowering risk during the early years 
of testing. However, a significant amount of ground and flight tests 
remains over the next 6 years. All three variants need to demonstrate 
their flight performance. The carrier variant will be the last of the 
three variants to be delivered to the flight test program. It is now 
scheduled to start flight testing in May 2009 and has nearly 900 flight 
tests planned to demonstrate its flight performance. If the program 
executes its plan for a steep ramp up in production before proving the 
basic flying qualities of each aircraft variant, the likelihood of 
costly changes to its significant investment in production will remain 
high. 

Recommendation for Executive Action: 

To improve chances of a successful outcome, we are recommending that 
the Secretary of Defense limit annual low-rate initial production 
quantities to no more than 24 aircraft per year, the current 
manufacturing capacity, until each variant's basic flying qualities 
have been demonstrated in flight testing now scheduled in the 2010 time 
frame. 

Agency Comments and our Evaluation: 

DOD provided us with written comments on a draft of this report. The 
comments appear in appendix II. 

DOD non-concurred with our recommendation stating that the current JSF 
acquisition strategy provides an effective balance of technical risk, 
financial constraints, and operational needs of the services. However, 
we believe DOD's actions to reduce aircraft quantities in the fiscal 
year 2008 President's Budget are in line with our recommendation to 
limit production to current manufacturing capacity until each variant's 
flying qualities have been demonstrated in flight testing. In the 2008 
budget, DOD reduced the number of production aircraft it plans to buy 
during the flight test program by about 35 percent as compared to its 
previous plan for the JSF. Under this new plan DOD does not 
substantially increase its buy quantities of production aircraft until 
2011. We continue to believe that limiting production quantities until 
the design is demonstrated would reduce the overlap in production and 
development while still allowing the efficient transition from 
development to production. It would also make cost and schedule more 
predictable and lessen the risk to DOD's production investment. The JSF 
program is still only in its sixth year of a 12-year development 
program with significant challenges remaining such as completing the 
design, software development, and flight testing. As such, there is 
continued risk that testing will not go as planned and demonstrating 
the aircraft's capability could be delayed beyond the current plan. 
Therefore, we maintain our recommendation and will continue to monitor 
the progress in the test program and the resulting dynamics between 
development and production. 

We are sending copies of this report to the Secretary of Defense; the 
Secretaries of the Air Force, Army, and Navy; and the Director of the 
Office of Management and Budget. We will also provide copies to others 
on request. In addition, the report will be made available at no charge 
on the GAO Web site at http://www.gao.gov. 

If you or your staff have any questions concerning this report, please 
contact me at (202) 512-4841. Contact points for our offices of 
Congressional Relations and Public Affairs may be found on the last 
page of this report. Other staff making key contributions to this 
report were Michael Hazard, Assistant Director; Lily Chin; Matthew Lea; 
Gary Middleton; Daniel Novillo; Karen Sloan; Brian Smith, Adam 
Vodraska; and Joe Zamoyta. 

Signed by: 

Michael J. Sullivan: 
Director: 
Acquisition and Sourcing Management: 

List of Congressional Committees: 

The Honorable Carl Levin: 
Chairman: 
The Honorable John McCain: 
Ranking Minority Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Daniel K. Inouye: 
Chairman: 
The Honorable Ted Stevens: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
United States Senate: 

The Honorable Ike Skelton: 
Chairman: 
The Honorable Duncan L. Hunter: 
Ranking Minority Member: 
Committee on Armed Services: 
House of Representatives: 

The Honorable John P. Murtha: 
Chairman: 
The Honorable C.W. Bill Young: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

[End of section] 

Appendix I: Scope and Methodology: 

To determine the status of the Joint Strike Fighter (JSF) program's 
cost, schedule, and performance, we compared current program estimates 
against estimates established after the program rebaselined in fiscal 
year 2004. Current official program cost estimates are based on the 
program's December 31, 2005, Selected Acquisition Report to Congress. 
At the time of our review, the Office of the Secretary of Defense was 
still preparing its new cost estimate to be included in the program's 
Selected Acquisition Report dated December 31, 2006, expected to be 
delivered to the Congress in April 2007. Because the new official cost 
estimate for the JSF program will not be available until after this 
report is issued we are unable to make informed judgments on those 
estimated costs. It should be noted that after our 2006 report was 
issued on March 15, 2006, DOD released its December 2005 Selected 
Acquisition Report, which showed an increase of over $19 billion in 
total estimated JSF program costs. 

We identified changes in the program's cost, schedule, and performance 
since the program rebaseline and analyzed relevant information to 
determine the primary causes of those changes. We reviewed JSF 
management reports, acquisition plans, test plans, risk assessments, 
cost reports, independent program assessments, and program status 
briefings. We interviewed officials from the DOD acquisition program 
management office and prime contractor to gain their perspectives on 
the performance of the program. 

To identify the challenges the program will face in the future, we 
compared the programs plans and results to date with future plans to 
complete development. We analyzed design and manufacturing data from 
the program office and the prime contractor to evaluate performance and 
trends. We reviewed program risk reports, earned value management data, 
and manufacturing data to identify uncertainties and risks to 
completing the program within the new targets established by the 
program rebaseline. We analyzed test program and software data to 
understand the readiness and availability of development aircraft for 
the test program. We also obtained information on past DOD programs 
from Selected Acquisition Reports and prior work conducted by GAO over 
the past two decades. We interviewed officials and reviewed reports 
from several DOD independent oversight organizations to gain their 
perspectives on risk in the program. 

To assess the likely impacts of concurrently developing and 
manufacturing JSF aircraft we compared the program's plans and results 
to date against best practice standards for applying knowledge to 
support major program investment decisions. The best practice standards 
are based on a GAO body of work that encompasses 10 years and visits to 
over 25 major commercial companies. Our work has shown that valuable 
lessons can be learned from the commercial sector and can be applied to 
the development of weapons systems. We identified gaps in product 
knowledge at the production decision, reasons for these gaps, and the 
risks to the program. We also examined the F-22A program's acquisition 
approach. We interviewed officials from the DOD acquisition program 
management office and prime contractor to gain their perspectives on 
program risks and their approaches to managing risks. 

In performing our work, we obtained information and interviewed 
officials from the JSF Joint Program Office, Arlington, Virginia; F-22A 
Program Office, Wright-Patterson Air Force Base, Ohio; Lockheed Martin 
Aeronautics, Fort Worth, Texas; Defense Contract Management Agency, 
Fort Worth, Texas; and offices of the Director, Operational Test and 
Evaluation, and Acquisition, Technology and Logistics, Program Analysis 
and Evaluation-Cost Analysis Improvement Group, which are part of the 
Office of Secretary of Defense in Washington, D.C. We performed our 
work from June of 2006 to March of 2007 in accordance with generally 
accepted government auditing standards. 

[End of section] 

Appendix II: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
3000 Defense Pentagon: 
Washington, DC 20301-3000: 
Acquisition, Technology And Logistics: 

Mar 5 2007: 

Mr. Michael J. Sullivan: 
Director, Acquisition and Sourcing Management: 
U.S. Government Accountability Office: 
441 G Street, N. W. 
Washington, D.C. 20548: 

Dear Mr. Sullivan: 

This is the Department of Defense response to the Government 
Accountability Office (GAO) draft report 07-360, "Joint Strike Fighter: 
Progress Made and Challenges Remain," dated January 26, 2007 (GAO Code 
120570). The Department non-concurs with the report recommendation, but 
appreciates the GAO's highlighting of both program successes and 
challenges. Details of the non-concurrence are contained in the 
enclosure. 

The Department values the opportunity to comment on the draft report 
and looks forward to continued discussions on the program with the GAO. 

Sincerely, 

Signed by: 

David G. Ahern: 
Director: 
Portfolio Systems Acquisition: 

Enclosure: 
As stated: 

GAO Draft Report - Dated January 26, 2007 GAO-07-360: 

"Joint Strike Fighter-Progress Made and Challenges Remain" 

Department Of Defense Comments To The Recommendation: 

Recommendation: To improve chances for a successful outcome, the GAO 
recommends the Secretary of Defense limit annual production quantities 
to no more than 24 aircraft per year, the current manufacturing 
capability, until each variant's basic flying qualities have been 
demonstrated in flight testing now scheduled in the 2010 timeframe. 

DOD Response: Non-concur. The current F-35 acquisition strategy 
provides the most effective balance of technical risk, financial 
constraints and the Services' operational needs. Fiscal constraints 
have driven the DoD's decision to reduce near-term quantities in the 
FY08 President's Budget. However, the program will continue to ramp up 
production rate, tooling, and support activities to meet operational 
needs. The program has an acceptable level of concurrency and an 
appropriate acquisition strategy. Eight international partners have 
also recently reasserted their confidence in the F-35 acquisition 
strategy by signing the Production, Sustainment and Follow-on 
Development Memorandum of Understanding (MOU). 

The Department believes that a major manufacturing or design flaw, 
requiring extensive delay of the program, is unlikely. Furthermore, 
that risk is more than offset by the certainty of higher unit costs 
which the Department would incur if it accepted a lower ramp rate. The 
Department would also need to further extend legacy fleets past their 
current service life expectancies, including higher operating costs 
which would consume funds currently targeted for recapitalization/ 
modernization efforts. Allied Services committed to this program and 
would be similarly impacted. The Department believes that restricting F-
35 annual production quantities as recommended by the GAO would further 
increase F-35 procurement costs, outpacing any potential retrofit costs 
to correct any future design deficiencies. 

Modern experience with both commercial and military aircraft supports 
the Department's position. The F-35 employs extensive use of modern 
digital design and development tools, ground test laboratories, 
modeling and simulation techniques and flying test beds to accelerate 
design maturation and burn-down development risk far ahead of flight 
test. The Department's confidence has been reinforced with the design, 
manufacturing, and flight test performance of the first F-35 flight 
test aircraft. Numerous other indicators from this aircraft--for 
example, actual weight within 1% of predicted, no fuel leaks during 
ground tests (unprecedented), high level of quality in manufacturing 
and assembly, and a high frequency of flight tests thus far--further 
increase Department confidence. The program is supported by thorough 
insight by the engineering expertise of the Navy and Air Force, and 
further reinforced by the outstanding data correlation between initial 
flight test results and modeling and simulation predictions. Similar 
experiences have been seen in the commercial sector, where both the 
Boeing 777 and 787 had virtual "roll-outs" and successfully adopted 
concurrent development and production strategies. 

The FY08 President's Budget Request proposes near-term reductions in 
the quantities of F-35s to be procured over the next five years, due to 
shortfalls in outyear Service funding (FY12 and FYI 3) and procurement 
and developmental cost growth in the program. A significant portion of 
the procurement cost growth cited by GAO is due to inflation factors, 
aggregate aerospace company financial performance, and the worldwide 
precious metals commodities market aspects that the F-35 program could 
not accurately project. The Department continues to monitor program 
performance and incentivize the contractor to keep unit costs in check. 
The Department will continue to hold annual Defense Acquisition Boards 
with stringent exit criteria before committing to further procurement 
investments. 

The Department agrees with several other concerns that the GAO 
identifies: 

* The planned flight test activity does not yet fit within the 
development schedule. The program has undertaken an intensive review of 
its verification strategy in order to reduce the number of flight tests 
without sacrificing the level of fidelity needed to verify performance. 

* Software and integration is a challenge in 2007 and 2008. The 
Department will closely track software productivity and frequently 
revisit its assumptions about how many lines of code it can execute 
with the dollars and schedule remaining. Warfighter representatives are 
heavily involved in making the difficult trades, which will be critical 
to produce the most capable aircraft within these constraints. 

* Executing the remaining design tasks within the planned labor profile 
to meet the planned manufacturing dates will also be a challenge. The 
program has recently completed extensive productivity improvement plans 
and developed more efficient manufacturing and design processes. These 
will be watched closely in 2007 to ensure development costs do not 
spiral upwards. 

The Department is pleased that the GAO recognized the F-35 program's 
progress. Specifically, the report appropriately assesses the F-35 
program's performance from its current baseline. The report recognizes 
some of the many steps the program office and contractor have taken to 
be responsive to problems to date. Finally, it acknowledges that some 
program concurrency is helpful in making the transition from 
development to production, and that the program is viable given 
progress to-date. 

[End of section] 

(120570) 

FOOTNOTES 

[1] Section 213 of the Act requires us to assess the extent to which 
the system development and demonstration program is currently meeting 
cost, schedule, and performance goals; the likelihood that the program 
will be completed within estimated costs; and the program's current 
acquisition plan leading to production. 

[2] GAO, Joint Strike Fighter: DOD Plans to Enter Production before 
Testing Demonstrates Acceptable Performance, GAO-06-356 (Washington 
D.C.: Mar. 15, 2006) and Tactical Aircraft: Opportunity to Reduce Risks 
in the Joint Strike Fighter Program with Different Acquisition 
Strategy, GAO-05-271 (Washington D.C.: Mar. 15, 2005). 

[3] In section 211 of the John Warner National Defense Authorization 
Act for Fiscal Year 2007 (P.L. 109-364), Congress required independent 
cost analyses of the alternate engine program by March 15, 2007, from 
the DOD Cost Analysis Improvement Group, a Federally Funded Research 
and Development Center selected by DOD, as well as GAO. 

[4] Critical design review for the carrier variant has been rescheduled 
from late 2006 to spring 2007. According to program officials, this 
delay will allow the program to mature the design of the variant. 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts 
newly released reports, testimony, and correspondence on its Web site. 
To have GAO e-mail you a list of newly posted products every afternoon, 
go to www.gao.gov and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 441 G Street NW, Room LM 
Washington, D.C. 20548: 

To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202) 
512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S. 
Government Accountability Office, 441 G Street NW, Room 7125 
Washington, D.C. 20548: 

Public Affairs: 

Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800 
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, D.C. 20548: