GAO reviewed the construction schedule and cost status of the Denver International Airport. GAO found that: (1) as of July 1992, construction was on schedule, with 41 percent completed; (2) as of August 1992, the total cost was estimated to be $4 billion; (3) although costs of 27 contracts cited in its September 1991 report have increased about 5 percent due to change orders, the contracts remained about $89 million under their budgeted amount; (4) 83 percent of needed funds for the airport will come from unsecured revenue bonds, with the rest from federal grants, and passenger fees and excess revenues from Stapleton International Airport; (5) two of the four largest all-cargo carriers have decided to operate at the new airport rather than a smaller airport after officials relocated the cargo facilities at the new airport; (6) future cargo losses to the smaller airport could reduce revenues to the new airport, and increase fees to other users; and (7) expansion of the smaller airport for cargo operations would require greater federal expenditures, could potentially cause greater environmental impacts, and could delay flights at the new airport.

Full Report

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

AirportsConstruction contractsConstruction costsContract performanceFacility constructionFederal grantsFuture budget projectionsAirlinesAviationFreight transportation