Pursuant to a congressional request, GAO reviewed 22 selected Navy shipbuilding contracts to determine the effects of increased competition, focusing on: (1) whether the Navy can execute the contracts within the funding appropriated; (2) the status of current and future claims against the government; (3) the actions that the Navy is taking to address current and anticipated claims; and (4) whether current staffing levels are providing effective contract oversight.

Full Report

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Competitive procurementConstruction contractsContract administrationContract costsContract oversightContractor paymentsCost overrunsNaval procurementQuestionable procurement chargesShipbuilding industry