Contested Procurement:

Washington Metropolitan Area Transit Authority and Everson Electric

RCED-86-229BR: Published: Sep 25, 1986. Publicly Released: Oct 10, 1986.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO: (1) investigated the Washington Metropolitan Area Transit Authority's (WMATA) decision to award a contract for the repair and overhaul of 48 railcar traction motors to one firm and deny a subsequent bid protest from another firm; and (2) provided information on the WMATA disadvantaged business enterprises (DBE) procurement procedures.

GAO found that WMATA: (1) complied with the DBE procurement procedures; (2) properly awarded the contract and denied the bid protest since the protester failed to meet a material solicitation requirement; and (3) properly rejected the protester's bid because it failed to comply with DBE procedures.

Sep 28, 2018

Sep 20, 2018

Sep 17, 2018

Sep 12, 2018

Sep 5, 2018

Aug 30, 2018

Aug 27, 2018

Aug 15, 2018

Jul 30, 2018

Jul 26, 2018

Looking for more? Browse all our products here