National Ignition Facility:
Management and Oversight Failures Caused Major Cost Overruns and Schedule Delays
RCED-00-141: Published: Aug 8, 2000. Publicly Released: Aug 16, 2000.
Additional Materials:
- Full Report:
Contact:
(202) 512-3000
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
Pursuant to a congressional request, GAO provided information on the Department of Energy's (DOE) National Ignition Facility (NIF), focusing on the: (1) magnitude of NIF's cost and schedule overruns; (2) reasons for these cost and schedule problems; (3) effects of NIF's cost and schedule on other weapons and science programs; and (4) DOE's and Lawrence Livermore's actions to correct these problems.
GAO noted that: (1) DOE and Lawrence Livermore now estimate that NIF will eventually cost about $3.3 billion and will be completed in 2008; (2) these new estimates mean NIF will cost over $1 billion more than originally planned and take 6 years longer to complete; (3) however, on the basis of analysis of figures from DOE and Lawrence Livermore, GAO estimates that NIF's cost is closer to $4 billion because DOE's estimate does not include all research and development costs from other program areas that are needed to support NIF; (4) furthermore, since significant research and development activities to support NIF remain to be completed and technical uncertainties persist, the cost of NIF could grow even higher and completion could take even longer; (5) NIF's cost increases and schedule delays were caused by a combination of poor Lawrence Livermore management and inadequate DOE oversight; (6) since NIF's beginning, the absence of effective independent reviews has enabled the project's costs and schedules to grow undetected by DOE program officials at headquarters and at Lawrence Livermore; (7) furthermore, none of these reviews has examined both the construction project and its supporting research and development activities; (8) paying for NIF's cost overruns has broad implications for DOE's nuclear weapons program; (9) the Secretary of Energy has said he wants to complete NIF but will not ask Congress for additional appropriations to pay for NIF's cost increases; (10) instead, he announced that the Department will pay for NIF's overruns by reallocating funds from within DOE's existing nuclear weapons budget; (11) however, DOE has not fully disclosed which programs will be cut to pay for NIF, nor when or how this will be done; (12) nor has DOE evaluated how this reallocation will affect components of the nuclear weapons program that might be eliminated, reduced in scope, or extended in order to fund NIF; (13) DOE tried but was unable to secure agreement among its three weapons laboratories that will use NIF--Lawrence Livermore, Los Alamos, and Sandia; (14) consequently, DOE's June "interim" cost and schedule plan was not developed by taking into account the many potential impacts on DOE's nuclear weapons program; and (15) in addition, because DOE has not determined how it intends to pay for NIF's cost overruns, the potential impacts on other science programs are unknown.
Recommendations for Executive Action
Status: Closed - Implemented
Comments: In 2003 and 2004, two independent committees assessed NIF's technical performance and project performance against established cost and schedule baselines. Each review committee was comprised of experts from government, industry, and universities who had no responsibility for NIF. According to the NIF project director, these technical reviews met the general criteria of independence. Prior to these outside reviews, NIF's Program Review Committee conducted several reviews that, according to NIF's project director, resulted in intense discussions of technical issues even though several committee members had connections with the NIF project.
Recommendation: To ensure that DOE has an effective independent review of NIF, the Secretary of Energy should arrange for an outside scientific and technical review of NIF's remaining technical challenges as they relate to the project's cost and schedule risks.
Agency Affected: Department of Energy
Status: Closed - Implemented
Comments: DOE's Fiscal Year (FY) 2005 Budget Justification, released in February 2004, showed that NNSA has extended the National Ignition Facility's (NIF) target date for demonstrating ignition from FY 2010 to FY 2014. Despite this 4-year delay, NNSA will be able to use NIF's capabilities during the interim to conduct critical Stockpile Stewardship research. However, the extension will effectively reduce adverse budgetary impacts on other Stockpile Stewardship programs because NIF's program costs have substantially exceeded NNSA's estimate in 2000.
Recommendation: To ensure an appropriate balance between NIF and the rest of the nuclear weapons program, the Secretary of Energy should not reallocate funds from the nuclear weapons program to NIF until DOE: (1) evaluates the impact of its cost and schedule plan, as well as any other options for NIF, on the overall nuclear weapons program; and (2) certifies that the selected NIF cost and schedule plan will not negatively affect the balance of the Stockpile Stewardship Program.
Agency Affected: Department of Energy
Explore the full database of GAO's Open Recommendations
»
Jan 19, 2021
-
Federal Rulemaking:
Selected EPA and HHS Regulatory Analyses Met Several Best Practices, but CMS Should Take Steps to Strengthen Its AnalysesGAO-21-151: Published: Dec 17, 2020. Publicly Released: Jan 19, 2021.
Jan 13, 2021
-
Department of Energy Contracting:
Improvements Needed to Ensure DOE Assesses Its Full Range of Contracting Fraud RisksGAO-21-44: Published: Jan 13, 2021. Publicly Released: Jan 13, 2021.
Dec 16, 2020
-
Data Governance:
Agencies Made Progress in Establishing Governance, but Need to Address Key MilestonesGAO-21-152: Published: Dec 16, 2020. Publicly Released: Dec 16, 2020.
Dec 9, 2020
-
2020 Census:
The Bureau Concluded Field Work but Uncertainty about Data Quality, Accuracy, and Protection RemainsGAO-21-206R: Published: Dec 9, 2020. Publicly Released: Dec 9, 2020.
Dec 3, 2020
-
2020 Census:
Census Bureau Needs to Assess Data Quality Concerns Stemming from Recent Design ChangesGAO-21-142: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020. -
2020 Census:
Census Bureau Needs to Ensure Transparency over Data QualityGAO-21-262T: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020.
Nov 30, 2020
-
Federal Buying Power:
OMB Can Further Advance Category Management Initiative by Focusing on Requirements, Data, and TrainingGAO-21-40: Published: Nov 30, 2020. Publicly Released: Nov 30, 2020.
Nov 24, 2020
-
Disaster Response:
Agencies Should Assess Contracting Workforce Needs and Purchase Card Fraud RiskGAO-21-42: Published: Nov 24, 2020. Publicly Released: Nov 24, 2020.
Nov 23, 2020
-
Federal Contracting:
Actions Needed to Improve Department of Labor's Enforcement of Service Worker Wage ProtectionsGAO-21-11: Published: Oct 29, 2020. Publicly Released: Nov 23, 2020.
Nov 18, 2020
-
Federal Telework:
Key Practices That Can Help Ensure the Success of Telework ProgramsGAO-21-238T: Published: Nov 18, 2020. Publicly Released: Nov 18, 2020.
Looking for more? Browse all our products here