Cost Overrun on the Aeropropulsion Systems Test Facility
PLRD-82-123: Published: Sep 30, 1982. Publicly Released: Sep 30, 1982.
Additional Materials:
- Full Report:
Contact:
GAO reviewed the reasons for the cost overrun on the Aeropropulsion Systems Test Facility (ASTF) construction process and discussed the construction of the Space Transportation System (STS) support facilities with Air Force and Army Corps of Engineers officials to determine whether the design responsibilities for these facilities were split between the Air Force and the Corps in ways similar to the ways in which they were split on the ASTF.
The ASTF was supposedly fully funded at $437 million in 1977 but, since that time, it has experienced a significant cost overrun, estimated at $138.4 million. The Air Force entered into the construction contract with a design that was not well suited to its revised procurement plan which provided for two concurrent procurements, one for construction and the other for the acquisition of equipment. Some of the equipment used created facility interface problems and required modification of the original design. In addition, the concurrent procurement resulted in numerous design omissions. While the Corps, as construction agent, performed a constructibility review, it was not funded to perform a design review. Inadequate management also contributed to the overrun. Project progress monitoring was lax and this delayed recognition of the extent of the equipment interface problem and its effect on the project. If properly implemented, proposed Air Force policy and management changes should enable the Air Force to better control large, complex projects such as the ASTF. The management responsibilities for the design of the ASTF and STS projects are similarly divided between the Air Force and the Corps. However, unlike the ASTF, the STS support facilities do not have Government-furnished equipment. Therefore, the ASTF design problems due to interface requirements will not occur on the STS project.
Dec 22, 2020
-
Commercial Space Transportation:
FAA Should Examine a Range of Options to Support U.S. Launch InfrastructureGAO-21-154: Published: Dec 22, 2020. Publicly Released: Dec 22, 2020.
Dec 15, 2020
-
NASA Human Space Exploration:
Significant Investments in Future Capabilities Require Strengthened Management OversightGAO-21-105: Published: Dec 15, 2020. Publicly Released: Dec 15, 2020.
Apr 30, 2020
-
Priority Open Recommendations:
National Aeronautics and Space AdministrationGAO-20-526PR: Published: Apr 23, 2020. Publicly Released: Apr 30, 2020.
Apr 29, 2020
-
NASA:
Assessments of Major ProjectsGAO-20-405: Published: Apr 29, 2020. Publicly Released: Apr 29, 2020.
Jan 29, 2020
-
NASA Commercial Crew Program:
Significant Work Remains to Begin Operational Missions to the Space StationGAO-20-121: Published: Jan 29, 2020. Publicly Released: Jan 29, 2020.
Jan 28, 2020
-
James Webb Space Telescope:
Technical Challenges Have Caused Schedule Strain and May Increase CostsGAO-20-224: Published: Jan 28, 2020. Publicly Released: Jan 28, 2020.
Dec 19, 2019
-
NASA Lunar Programs:
Opportunities Exist to Strengthen Analyses and Plans for Moon LandingGAO-20-68: Published: Dec 19, 2019. Publicly Released: Dec 19, 2019.
Sep 18, 2019
-
NASA:
Actions Needed to Improve the Management of Human Spaceflight ProgramsGAO-19-716T: Published: Sep 18, 2019. Publicly Released: Sep 18, 2019.
Jun 20, 2019
-
NASA Commercial Crew Program:
Schedule Uncertainty Persists for Start of Operational Missions to the International Space StationGAO-19-504: Published: Jun 20, 2019. Publicly Released: Jun 20, 2019.
Jun 19, 2019
-
NASA Human Space Exploration:
Persistent Delays and Cost Growth Reinforce Concerns over Management of ProgramsGAO-19-377: Published: Jun 19, 2019. Publicly Released: Jun 19, 2019.
Looking for more? Browse all our products here