Skip to main content

Johnston Atoll Contractor Performance

NSIAD-96-22R Published: Oct 06, 1995. Publicly Released: Oct 06, 1995.
Jump To:
Skip to Highlights

Highlights

GAO reviewed the performance of the Johnston Atoll operation and maintenance contractor. GAO noted that: (1) the operation and maintenance contractor's performance rating dropped by about 25 percent between 1987 and 1991; (2) in 1991, the Army encouraged the contractor to improve its performance by offering financial incentives; (3) although the contractor's performance did not significantly improve between 1992 and 1994, it received an additional $5 million in award fees; (4) the contract award fee structure, delays in determining award fees, and ineffective communications resulted in lower than expected performance levels; and (5) although the Army and the contractor are working together to improve facility operations, management improvements could be enhanced if the Army adopted a management team approach called partnering at the facility.

Recommendations

Recommendations for Executive Action

Agency Affected Recommendation Status
Other The Assistant to the Secretary of Defense for Atomic Energy should ensure that the Commander of the Army Chemical Demilitarization and Remediation Activity develops a new contract award fee structure that recognizes the base fee as compensation for acceptable performance and requires the contractor to perform above the acceptable level to earn an additional award fee.
Closed – Implemented
The new JACADS contract, awarded in 1998, establishes a 3-percent base award fee as compensation for acceptable performance and a 6-percent incentive award fee. The award fee criteria are structured so that the award fee is only paid on performance above acceptable performance levels.
Other The Assistant to the Secretary of Defense for Atomic Energy should ensure that the Commander of the Army Chemical Demilitarization and Remediation Activity determines and provides the award fees within the 60-day contractual period.
Closed – Implemented
The Army agreed that efforts were needed to shorten the timeframe from the availability of cost data to the date of the award fee. However, the Army concluded that 60 days was too short and that a 90-day window was more appropriate. As a result, the Army established a 90-day goal for awarding the fee for JACADS.
Other The Assistant to the Secretary of Defense for Atomic Energy should ensure that the Commander of the Army Chemical Demilitarization and Remediation Activity formalizes the government's intention to continue its team approach to managing the Johnston Atoll facility by proposing the partnering approach during the 1996 contract negotiations.
Closed – Implemented
The Army held formal discussions with the JACADS systems contractor that resulted in a partnering agreement becoming part of the new contract. Since then, the Army has conducted several smaller contract administrative meetings refining the partnering approach with the JACADS systems contractor. Further, this approach has been used during recent planning efforts for closing the disposal facility.

Full Report

Office of Public Affairs

Topics

Army facilitiesChemical warfareContract administrationContract performanceContractor paymentsCost plus award fee contractsDepartment of Defense contractorsMunitionsProperty disposalMilitary forces