Delivery Problems With Inertial Measurement Units

NSIAD-88-74BR: Published: Dec 18, 1987. Publicly Released: Jan 12, 1988.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO provided information on the Air Force's acquisition of inertial measurement units (IMU), a major component of the Peacekeeper missile guidance and control system.

GAO found that: (1) the IMU manufacturer did not timely deliver the units, resulting in a 4.5-month delay in the deployment schedule; (2) although the manufacturer expects to be back on schedule by April 1988, the Air Force believes that October is a more realistic date; (3) changes in the production date from 1983 to 1984 without any changes in the operational capability date caused delays; and (4) as of September 30, 1987, only 18 of the 28 Peacekeeper missiles available for operations were on alert because of shortages of IMU. GAO also found that: (1) the Air Force relaxed its acquisition procedures in order to accommodate the manufacturer's inability to effectively manage its manufacturing process; (2) 17 test flights for IMU accuracy and reliability had better-than-anticipated results; and (3) the Air Force will absorb about $17 million of an estimated $24.4 million in total contract costs because of delivery delays.

Apr 24, 2018

Apr 18, 2018

Apr 12, 2018

Apr 11, 2018

Mar 30, 2018

Mar 22, 2018

Mar 14, 2018

Looking for more? Browse all our products here