Federal Construction:
Army Corps of Engineers and GSA Need to Improve Data on Contract Changes
GAO-19-500: Published: Jul 2, 2019. Publicly Released: Jul 2, 2019.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-4841
woodsw@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
The government spends billions annually on construction projects. Contract changes, common on such projects, can delay payments and create challenges for contractors, particularly small businesses.
We looked at construction contract changes at two agencies with large construction budgets: the U.S. Army Corps of Engineers and the General Services Administration. We found neither agency regularly tracks how long it takes to process contract changes, which makes it more difficult for them to identify and respond to problems.
We recommended these agencies each develop a strategy to monitor how long construction contract changes take.
A hardhat, office blueprints, and assorted office supplies on a desk.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-4841
woodsw@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
Multiple factors affect the time it takes to finalize a construction contract change. For example, preparing cost estimates can be time consuming, particularly for complex changes. Yet the time may be used to help ensure the government has adequate cost data to inform negotiations. In addition, according to agency officials, miscommunication during the contract change process—which can lead to problems such as unauthorized work undertaken by the contractor—can result in additional reviews and longer time frames. According to U.S. Army Corps of Engineers (USACE) data, most of its construction contract changes are finalized within 60 days. Some take much longer, however (see figure).
Time Frames for Finalizing Construction Contract Changes at the U.S. Army Corps of Engineers, 2013 through 2018
Note: The General Services Administration's (GSA) Public Buildings Service could not provide similar data.
Agency officials and industry representatives agreed that perceptions differ about the length of the contract change process. For example, because a change can impact the contractor's cost and schedule immediately, the contractor typically perceives that the process starts earlier—and lasts longer—than the government does.
Neither GSA nor USACE regularly monitors how long it takes to finalize construction contract changes, limiting management's ability to identify and respond to problems. Internal controls require agencies to collect and use quality data for management purposes such as monitoring agency activities. GSA systems do not collect data that permit analysis of contract change timeframes at the headquarters level. USACE systems produce contract change data for its districts, but data consolidation and calculations must be done manually and are not done regularly. Neither agency has a strategy in place to address these issues. Without regular review of these timeframes, USACE and GSA contracting officials may be unaware of any existing or potential problems, such as long process times that may affect project schedules. In addition, these data system limitations are likely to create difficulties for agencies when providing the information required by new legislation.
Why GAO Did This Study
In fiscal year 2018, federal agencies spent more than $36 billion on construction contracts, with more than 45 percent going to small business. Typically, construction projects involve some degree of change as the project progresses. Some federal construction contractors have raised concerns that delays in processing contract changes and making payments creates challenges, particularly for small businesses. Section 855 of the National Defense Authorization Act for Fiscal Year 2019 requires agencies to report information related to how quickly they finalize contract changes.
GAO was asked to review federal construction contract change processes and timeframes. GAO (1) identified factors that affect the time it takes to finalize contract changes, and (2) assessed the extent to which selected agencies monitor time frames for finalizing contract changes. GAO reviewed relevant regulations and agency policies, analyzed available data, and interviewed officials from GSA's Public Buildings Service and USACE—two agencies with large amounts of obligations on construction—and two industry associations.
What GAO Recommends
GAO is making two recommendations: that GSA's Public Buildings Service and USACE each develop a strategy to routinely collect information on and monitor time frames for construction contract changes at the headquarters level. Both agencies concurred with our recommendation.
For more information, contact William T. Woods at (202) 512-4841 or woodsw@gao.gov.
Recommendations for Executive Action
Status: Open
Comments: GSA agreed with this recommendation. In September 2019, GSA told us that it will set up a cross functional team with officials from the Public Building Service offices of Acquisitions and Design and Construction, and the GSA Office of Government-wide Policy, to develop a strategic plan to address the recommendation. In July 2020, GSA told us that the final action step for this recommendation was due to be completed on August 31, 2020. We will continue to monitor implementation of this recommendation as we receive more information on steps taken.
Recommendation: The Administrator of General Services should ensure that the Commissioner of the Public Buildings Service develops a strategy that outlines the steps needed to routinely collect information on and monitor the time frames for finalizing construction contract changes at the headquarters level. The strategy could address issues such as the types of construction contract changes that should be included, when the measurement of the contract change process should begin, and the information systems that will be affected. (Recommendation 1)
Agency Affected: General Services Administration
Status: Open
Comments: DOD agreed with this recommendation. In July 2020, DOD officials told us that it has developed a corrective action plan to address the recommendation, which is estimated to be completed at the end of August 2020. We will continue to monitor progress once we receive the corrective action plan.
Recommendation: The Secretary of the Army should direct the Chief of Engineers and Commanding General of the U.S. Army Corps of Engineers to develop a strategy to expand on existing data and systems to routinely collect information on and monitor the time frames for finalizing construction contract changes at the headquarters level. (Recommendation 2)
Agency Affected: Department of Defense: Department of the Army
Explore the full database of GAO's Open Recommendations
»
Jan 19, 2021
-
Federal Rulemaking:
Selected EPA and HHS Regulatory Analyses Met Several Best Practices, but CMS Should Take Steps to Strengthen Its AnalysesGAO-21-151: Published: Dec 17, 2020. Publicly Released: Jan 19, 2021.
Jan 13, 2021
-
Department of Energy Contracting:
Improvements Needed to Ensure DOE Assesses Its Full Range of Contracting Fraud RisksGAO-21-44: Published: Jan 13, 2021. Publicly Released: Jan 13, 2021.
Dec 16, 2020
-
Data Governance:
Agencies Made Progress in Establishing Governance, but Need to Address Key MilestonesGAO-21-152: Published: Dec 16, 2020. Publicly Released: Dec 16, 2020.
Dec 9, 2020
-
2020 Census:
The Bureau Concluded Field Work but Uncertainty about Data Quality, Accuracy, and Protection RemainsGAO-21-206R: Published: Dec 9, 2020. Publicly Released: Dec 9, 2020.
Dec 3, 2020
-
2020 Census:
Census Bureau Needs to Assess Data Quality Concerns Stemming from Recent Design ChangesGAO-21-142: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020. -
2020 Census:
Census Bureau Needs to Ensure Transparency over Data QualityGAO-21-262T: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020.
Nov 30, 2020
-
Federal Buying Power:
OMB Can Further Advance Category Management Initiative by Focusing on Requirements, Data, and TrainingGAO-21-40: Published: Nov 30, 2020. Publicly Released: Nov 30, 2020.
Nov 24, 2020
-
Disaster Response:
Agencies Should Assess Contracting Workforce Needs and Purchase Card Fraud RiskGAO-21-42: Published: Nov 24, 2020. Publicly Released: Nov 24, 2020.
Nov 23, 2020
-
Federal Contracting:
Actions Needed to Improve Department of Labor's Enforcement of Service Worker Wage ProtectionsGAO-21-11: Published: Oct 29, 2020. Publicly Released: Nov 23, 2020.
Nov 18, 2020
-
Federal Telework:
Key Practices That Can Help Ensure the Success of Telework ProgramsGAO-21-238T: Published: Nov 18, 2020. Publicly Released: Nov 18, 2020.
Looking for more? Browse all our products here