Global Positioning System:
Updated Schedule Assessment Could Help Decision Makers Address Likely Delays Related to New Ground Control System
GAO-19-250: Published: May 21, 2019. Publicly Released: May 21, 2019.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-4841
chaplainc@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
Americans rely on the Global Positioning System daily. The Defense Department is working to upgrade the systems that make up GPS, including completing a critical new ground control system known as OCX.
We found that the OCX upgrade—already delayed approximately 5 years—will likely be delayed further. At least 2 years of work remain. The OCX contractor has already used most of the extra time built into its schedule, leaving little room to fix any problems that may arise.
We recommended an independent assessment of the OCX schedule, which would allow the Defense Department and Congress to better plan how to deal with potential delays.
The OCX system will control GPS satellites from the ground

Conceptual illustration of OCX system, including a satellite dish, the earth, and orbiting satellites.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-4841
chaplainc@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
The Global Positioning System's (GPS) next generation operational control system's (OCX) program schedule continues to be optimistic and, with significant development remaining, more delays are likely for delivery, acceptance, and operation. See the figure below for previous delays, cost growth, and the current baseline.
Next Generation Operational Control System Cost and Schedule Baseline Growth from Program Development Start to Operations

Completing the full OCX program schedule requires (1) timely delivery by the contractor and acceptance by the Air Force and (2) an efficient completion of a planned 7-month government-run post-acceptance developmental testing. GAO found that there is potential for significant delays on both fronts. While there has been some improvement to the pace of software development, the rollout of the new development methodology has been delayed to a point where most of the contractor's schedule reserve has been used. Assumed improvements in how long it takes to repair software defects has not occurred as planned, placing additional pressure on the contractor's delivery date. Additionally, Air Force officials have acknowledged that the government developmental test period after acceptance could double in duration and delay operations further because of concurrency, test plan uncertainty, and risks of late discovery of problems.
With approximately 2 years of work remaining before delivery, there is no plan to have the full schedule independently assessed. For complex programs, such as OCX, best practices state an independent view is necessary and that a periodic schedule assessment should be performed as progress is made and risks change. Such an assessment would help inform congressional and DOD decision makers as they consider what steps may be taken to address delays to the start of OCX operations and ensure the investments in needed new receivers are properly aligned.
Why GAO Did This Study
The U.S. military and the public depend daily on GPS data. OCX, the ground system that will command and control next generation GPS satellites, is one of several interdependent systems the Air Force is developing to modernize GPS. OCX has been hampered by delays and $2.5 billion in cost growth since the program started in 2012. The Air Force set a new baseline for cost and schedule in 2018 after OCX breached its cost threshold in 2016.
The National Defense Authorization Act for Fiscal Year 2016 contained a provision that the Air Force provide quarterly reports to GAO on the next generation GPS acquisition programs, and a provision that GAO brief the defense committees as needed. GAO provided numerous briefings from 2016 through 2018 and issued reports in 2016 and 2017. Continuing this body of work, this report focuses on the extent to which schedule risks may affect OCX delivery, acceptance, and approval for operation.
GAO reviewed the Air Force's baseline review results, schedule risks, and progress, and applied selected best practices for cost and schedule management. GAO also reviewed OCX monthly management briefings and quarterly assessments, and interviewed officials from the OCX program office and Raytheon (the prime contractor), among others.
What GAO Recommends
GAO recommends that DOD conduct an independent schedule assessment of the full program schedule at the end of 2019. DOD did not concur with the recommendation. GAO believes the recommendation remains valid.
For more information, contact Cristina Chaplain at (202) 512-4841 or chaplainc@gao.gov.
Recommendation for Executive Action
Status: Open

Comments: DOD did not concur with our recommendation to conduct an independent assessment of the full OCX program schedule based on progress made through the end of calendar year 2019, citing an independent cost and schedule estimate conducted in September 2018 and other ongoing program assessment and monitoring efforts. GAO continues to affirm that the recommendation is necessary given that DOD has not conducted an assessment of the full schedule since June 2018, since which time program risks have evolved. Additionally, ongoing oversight efforts are limited in scope and do not include the developmental test period after product delivery. As of August 2020, the Air Force position remains a non-concur, based on the same rationale previously noted.
Recommendation: The Secretary of Defense should direct the Director, Office of Cost Assessment and Program Evaluation to conduct an independent schedule assessment of the full program schedule for the Global Positioning System's next generation operational control system based on progress made through the end of calendar year 2019. (Recommendation 1)
Agency Affected: Department of Defense
Explore the full database of GAO's Open Recommendations
»
Oct 21, 2020
-
Missile Defense:
Observations on Ground-based Midcourse Defense Acquisition Challenges and Potential Contract Strategy ChangesGAO-21-135R: Published: Oct 21, 2020. Publicly Released: Oct 21, 2020.
Oct 7, 2020
-
National Security:
Additional Actions Needed to Ensure Effectiveness of 5G StrategyGAO-21-155R: Published: Oct 7, 2020. Publicly Released: Oct 7, 2020.
Oct 1, 2020
-
Army Modernization:
Army Should Improve Use of Alternative Agreements and Approaches by Enhancing Oversight and Communication of Lessons LearnedGAO-21-8: Published: Oct 1, 2020. Publicly Released: Oct 1, 2020.
Sep 23, 2020
-
Nuclear Weapons:
NNSA Should Further Develop Cost, Schedule, and Risk Information for the W87-1 Warhead ProgramGAO-20-703: Published: Sep 9, 2020. Publicly Released: Sep 23, 2020.
Aug 20, 2020
-
Navy Shipyards:
Actions Needed to Address the Main Factors Causing Maintenance Delays for Aircraft Carriers and SubmarinesGAO-20-588: Published: Aug 20, 2020. Publicly Released: Aug 20, 2020.
Aug 14, 2020
-
GAO Audits Involving DOD:
Status of Efforts to Schedule and Hold Timely Entrance ConferencesGAO-20-690R: Published: Aug 14, 2020. Publicly Released: Aug 14, 2020.
Aug 6, 2020
-
Defense Workforce:
DOD Needs to Assess Its Use of Term and Temporary AppointmentsGAO-20-532: Published: Aug 6, 2020. Publicly Released: Aug 6, 2020. -
Next Generation Combat Vehicles:
As Army Prioritizes Rapid Development, More Attention Needed to Provide Insight on Cost Estimates and Systems Engineering RisksGAO-20-579: Published: Aug 6, 2020. Publicly Released: Aug 6, 2020.
Jul 30, 2020
-
National Nuclear Security Administration:
Information on the Fiscal Year 2021 Budget Request and Affordability of Nuclear Modernization ActivitiesGAO-20-573R: Published: Jul 30, 2020. Publicly Released: Jul 30, 2020.
Jul 27, 2020
-
Climate Resilience:
Actions Needed to Ensure DOD Considers Climate Risks to Contractors as Part of Acquisition, Supply, and Risk AssessmentGAO-20-511: Published: Jun 25, 2020. Publicly Released: Jul 27, 2020.
Looking for more? Browse all our products here

![defense icon, source: [West Covina, California] Progressive Management, 2008 defense icon, source: [West Covina, California] Progressive Management, 2008](https://www.gao.gov/images/rip/defense.jpg)
Explore our Key Issues on National Defense