Southwest Border Security:
CBP Is Evaluating Designs and Locations for Border Barriers but Is Proceeding Without Key Information
GAO-18-614: Published: Jul 30, 2018. Publicly Released: Aug 6, 2018.
Multimedia:
-
PODCAST: Southwest Border Security
Customs and Border Protection, under Homeland Security, is planning to construct barriers along our southwest border. We discuss their efforts in this podcast.
Additional Materials:
- View Report:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-8777
gamblerr@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
U.S. Customs and Border Protection (CBP) evaluated barrier design prototypes for the southwest border. CBP also determined how it would prioritize locations for future barriers, but didn't analyze the costs of putting barriers in each potential location. These costs can vary depending on topography, land ownership, and other factors.
Without assessing costs, CBP doesn't have complete information for prioritizing barrier deployments in the most cost-effective manner.
We recommended, among other things, further analysis of the costs to build future barriers.
U.S. Customs and Border Protection tested eight prototypes when considering designs for southwest border barriers.

Eight pictures of barrier prototypes near the southwest border. Some are concrete; some are constructed of other materials.
On December 10, 2018, GAO posted an HTML version of this report.
This report features a new HTML format that GAO is piloting in 2018.
To provide feedback on this format, e-mail contact@gao.gov
Multimedia:
-
PODCAST: Southwest Border Security
Customs and Border Protection, under Homeland Security, is planning to construct barriers along our southwest border. We discuss their efforts in this podcast.
Additional Materials:
- View Report:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-8777
gamblerr@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
In March 2017, U.S. Customs and Border Protection (CBP), within the Department of Homeland Security (DHS), issued two requests for proposals (RFP) for physical barrier prototype designs for the southwest border. One RFP was for prototypes made of reinforced concrete, the other was for prototypes made of other materials. CBP subsequently issued task orders, under contracts awarded to six companies, to design and construct eight prototypes, pictured below. From October to December 2017, CBP tested the prototypes, using a range of methods to attempt to climb and breach them. Based on the results, CBP identified design attributes it can use to customize future barrier designs for specific locations, depending on the terrain and other factors.
U.S. Customs and Border Protection's Barrier Prototype Designs

CBP and U.S. Border Patrol developed a methodology for prioritizing future barrier deployments along the entire southwest border, which included input from Border Patrol officials, data on illegal entry traffic, and analysis of operational and engineering feasibility for each potential location. However, the strategy did not include analysis of the costs associated with deploying barriers in each location or segment, which can vary depending on topography, land ownership, and other factors. Without assessing costs, consistent with leading practices for capital decision making, CBP does not have complete information for prioritizing locations to use its resources in the most cost-effective manner.
Acquisitions for the Border Wall System Program—DHS's program to deploy barriers and other assets along the southwest border—are required to follow the department's acquisition process. However, GAO found that for one of the two approved segments, DHS has not documented its plans as required. Specifically, GAO found that for the Rio Grande Valley segment, DHS leadership approved and documented plans in December 2017. In contrast, for the San Diego secondary barrier segment, CBP's plans have not yet been documented, which could hinder DHS's ability to monitor progress for the segment.
Why GAO Did This Study
In January 2017, the President issued Executive Order 13767, which directs the Secretary of Homeland Security to immediately plan, design, and construct a wall or other physical barriers along the southwest border. CBP's fiscal year 2018 appropriation provided funding for barrier planning and design, but limited use of funds for primary barrier construction to previously deployed fencing designs.
GAO was asked to review DHS's efforts to deploy barriers along the southwest border. This report examines (1) how CBP evaluated potential designs for barriers, (2) DHS's process for identifying and assessing locations for future deployments of barriers, and (3) how DHS is managing the acquisition of the Border Wall System Program, among other things.
GAO analyzed planning documents; interviewed DHS, CBP, and Border Patrol officials; and conducted a site visit to San Diego to observe CBP's testing of barrier prototypes. This is a public version of a sensitive report that GAO issued in June 2018. Information that DHS deemed sensitive has been omitted.
What GAO Recommends
GAO recommends that DHS analyze the costs associated with future barrier segments and include that analysis in future planning, and document plans for the planned secondary barrier replacement in the San Diego sector. DHS concurred with GAO's recommendations.
For more information, contact Rebecca Gambler at (202) 512-8777 or gamblerr@gao.gov.
Recommendations for Executive Action
Status: Open

Priority recommendation

Comments: In July 2018, we reported on U.S. Customs and Border Protection's (CBP) efforts to deploy new physical barriers along the southwest border. We found that the Impedance and Denial Prioritization Strategy-- CBP's strategy for prioritizing locations for future barrier deployments-- did not include analysis of the costs associated with deploying barriers in each location or segment, which can vary depending on topography, land ownership, and other factors. We recommended that CBP analyze the costs associated with future barrier segments and include cost as a factor in the Impedance and Denial Prioritization Strategy. CBP agreed with this recommendation. As of October 2018, Border Patrol plans to complete revisions to the prioritization process by September 2019. To fully implement our recommendation, Border Patrol needs to analyze the costs associated with future barrier segments and incorporate that analysis into its process for prioritizing new barrier segments across the southwest border.
Recommendation: The Commissioner of CBP should analyze the costs associated with future barrier segments and include cost as a factor in the Impedance and Denial Prioritization Strategy. (Recommendation 1)
Agency Affected: Department of Homeland Security
Status: Closed - Implemented

Comments: In July 2018, we reported on U.S. Customs and Border Protection's (CBP) efforts to deploy new physical barriers along the southwest border. We found that the Department of Homeland Security (DHS) had not documented its plans to follow the department's acquisition process for a planned barrier segment in San Diego. We recommended that the Under Secretary for Management document plans to require CBP to follow the DHS acquisition life cycle, including the completion of all acquisition documentation requirements, for the planned secondary barrier deployment in the San Diego sector. DHS agreed with this recommendation. In September 2018, the Under Secretary for Management approved the San Diego secondary barrier segment for Acquisition Decision Event (ADE) 2A/2B. In accordance with the DHS acquisition process, ADE-2A approves the program and ADE-2B approves the supporting projects and contracts. This action should serve to document the department's plans to follow the acquisition process for the planned segment. Therefore, this recommendation is closed as implemented.
Recommendation: The Under Secretary for Management should document plans to require CBP to follow the DHS acquisition life cycle, including the completion of all acquisition documentation requirements, for the planned secondary barrier deployment in the San Diego sector. (Recommendation 2)
Agency Affected: Department of Homeland Security
Explore the full database of GAO's Open Recommendations
»
Mar 7, 2019
-
Drug Policy:
Preliminary Observations on the 2019 National Drug Control StrategyGAO-19-370T: Published: Mar 7, 2019. Publicly Released: Mar 7, 2019.
Feb 27, 2019
-
Critical Infrastructure Protection:
Progress and Challenges in DHS's Management of Its Chemical Facility Security ProgramGAO-19-402T: Published: Feb 27, 2019. Publicly Released: Feb 27, 2019.
Feb 22, 2019
-
Department of Homeland Security:
Review of the Fiscal Year 2017 Entry/Exit Overstay ReportGAO-19-298R: Published: Feb 22, 2019. Publicly Released: Feb 22, 2019.
Feb 21, 2019
-
Coast Guard Shore Infrastructure:
Applying Leading Practices Could Help Better Manage Project Backlogs of at Least $2.6 BillionGAO-19-82: Published: Feb 21, 2019. Publicly Released: Feb 21, 2019.
Feb 7, 2019
-
Presidential Security:
Vetting of Individuals and Secure Areas at Mar-a-LagoGAO-19-246: Published: Jan 23, 2019. Publicly Released: Feb 7, 2019.
Feb 5, 2019
-
Presidential Travel:
Secret Service and DOD Need to Ensure That Expenditure Reports Are Prepared and Submitted to CongressGAO-19-178: Published: Jan 17, 2019. Publicly Released: Feb 5, 2019.
Jan 8, 2019
-
Federal Protective Service:
DHS Should Take Additional Steps to Evaluate Organizational PlacementGAO-19-122: Published: Jan 8, 2019. Publicly Released: Jan 8, 2019.
Dec 19, 2018
-
Critical Infrastructure Protection:
Actions Needed to Address Significant Weaknesses in TSA's Pipeline Security Program ManagementGAO-19-48: Published: Dec 18, 2018. Publicly Released: Dec 19, 2018.
Dec 13, 2018
-
National Security:
Long-Range Emerging Threats Facing the United States As Identified by Federal AgenciesGAO-19-204SP: Published: Dec 13, 2018. Publicly Released: Dec 13, 2018.
Dec 6, 2018
-
2017 Disaster Contracting:
Action Needed to Better Ensure More Effective Use and Management of Advance ContractsGAO-19-93: Published: Dec 6, 2018. Publicly Released: Dec 6, 2018.
Looking for more? Browse all our products here


Explore our Key Issues on Homeland Security