Coast Guard Acquisitions:

Actions Needed to Address Longstanding Portfolio Management Challenges

GAO-18-454: Published: Jul 24, 2018. Publicly Released: Jul 24, 2018.

Additional Materials:

Contact:

Marie A. Mak
(202) 512-4841
makm@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

The Coast Guard is spending billions of dollars to replace aging ships, aircraft, and other assets.

Because the Coast Guard has managed its acquisitions with a short-term, asset-by-asset focus, it has at times lost sight of the balance and cost of its overall asset portfolio. For example, some high-priority acquisitions have been delayed.

Also, the Coast Guard continues to operate its fleets for longer than originally planned, placing risk on its ability to accomplish its missions.

We recommended, among other things, that the Coast Guard annually assess the long-term affordability and balance of its acquisition portfolio.

The Offshore Patrol Cutter is the Coast Guard's highest acquisition priority

This is a photo of the Coast Guard's Offshore Patrol Cutter.

This is a photo of the Coast Guard's Offshore Patrol Cutter.

Additional Materials:

Contact:

Marie A. Mak
(202) 512-4841
makm@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

What GAO Found

The Coast Guard, a component within the Department of Homeland Security (DHS), continues to manage its acquisitions through its annual budget process and the 5-year Capital Investment Plan (CIP)—congressionally mandated and used for oversight. This management approach creates constant churn as program baselines must continually re-align with budget realities instead of budgets being formulated to support program baselines. Further, Coast Guard officials said the CIP reflects the highest priorities of the department—such as the Offshore Patrol Cutter, which is the Coast Guard's highest priority—and that trade-off decisions are made as part of the annual budget process. However, the effects of these decisions, such as which acquisitions would take on more risk so others can be prioritized and adequately funded, are not communicated in the CIP to key decision makers, because including such information is not statutorily required. Over the years, this approach has left the Coast Guard with a build up—or bow wave—of near-term unfunded acquisitions, negatively affecting recapitalization efforts and limiting the effectiveness of long-term planning. Including the effects of these trade-offs in the CIP would align with GAO's cost estimating best practices. Until it does so, the Coast Guard limits its ability to manage its acquisition portfolio in the long-term, beyond the time covered in the 5-year CIP.

The Coast Guard's Offshore Patrol Cutter

a  data-cke-saved-name=

In response to a September 2012 GAO recommendation, the Coast Guard updated the Executive Oversight Council's (EOC)—a cross-directorate group that oversees major acquisition programs—charter in 2014 to require annual reviews of the acquisition portfolio collectively. However, EOC officials said that these annual reviews never occurred, and GAO found that the annual review requirement was removed from the charter in 2017. Thus, the Coast Guard is without a senior-level group charged to collectively review and ensure affordability of its acquisition portfolio. The Office of Management and Budget's Capital Programming Guide states that a senior-level executive committee should be responsible for reviewing the agency's entire asset portfolio and for making decisions on the proper composition of assets needed to achieve strategic goals within budget constraints.

Why GAO Did This Study

The Coast Guard spends billions of dollars on its major acquisition programs to meet its missions. GAO's prior work has identified the Coast Guard's reliance on its annual budget process to manage its acquisition portfolio as a challenge.

GAO was asked to review the recapitalization of the Coast Guard's acquisition portfolio. This report assesses, among other topics, the extent to which the Coast Guard has made changes to how it manages its acquisition portfolio.

GAO assessed Coast Guard's major acquisition programs to determine changes since GAO's 2014 portfolio review. GAO analyzed program baselines and interviewed Coast Guard officials. GAO analyzed the CIP for fiscal years 2014 through 2018, and reviewed the EOC's documentation.

What GAO Recommends

GAO recommends that the annual CIPs reflect acquisition trade-off decisions and their effects, and that the EOC review the overall acquisition portfolio and its affordability annually. DHS concurred with the CIP recommendation. DHS did not concur with the EOC recommendation. It noted that other existing Coast Guard bodies are responsible for evaluating and prioritizing funding. However, DHS stated that the EOC charter will be updated to require it to review the overall acquisition portfolio, including long-term planning. If this long-term planning accounts for budget realities for the acquisition portfolio, GAO believes the intent of the recommendation will be met.

For more information, contact Marie A. Mak at (202) 512-4841 or makm@gao.gov.

Recommendations for Executive Action

  1. Status: Open

    Comments: The Coast Guard agreed with this recommendation but, as of August 2018, has not yet taken any action to implement it.

    Recommendation: The Commandant of the Coast Guard should work with Congress to include in the Coast Guard's annual 5-year CIP a discussion of the acquisition programs it prioritized that describes how trade-off decisions made could affect other acquisition programs, such as by delaying recapitalization efforts or needing to conduct Service Life Extension Projects for legacy assets. (Recommendation 1)

    Agency Affected: Department of Homeland Security: United States Coast Guard

  2. Status: Open

    Comments: The Coast Guard disagreed with this recommendation stating that other bodies within the Coast Guard--such as the Investment Board, Deputies Council, and Investment Review Board--are responsible for making decisions regarding out-year funding, while the Executive Oversight Council works outside of the annual budget process. DHS also stated that, to meet the spirit of our recommendation, the Coast Guard will update the Executive Oversight Council's charter to require a review of the collective acquisition portfolio, specifically evaluating long-term planning. We believe that updating the Executive Oversight Council's charter to include long-term-planning is a positive step. However, we continue to believe that in addition to long-term planning, the Executive Oversight Council should include the major acquisition portfolio's budget realities faced by the Coast Guard in its reviews, or long-term affordability. If the planning accounts for long-term funding considerations to achieve the Coast Guard's acquisition goals and objectives, we believe the intent of our recommendation would be met.

    Recommendation: The Commandant of the Coast Guard should require the Executive Oversight Council, in its role to facilitate a balanced and affordable acquisition portfolio, to annually review the acquisition portfolio collectively, specifically for long-term affordability. (Recommendation 2)

    Agency Affected: Department of Homeland Security: United States Coast Guard

 

Explore the full database of GAO's Open Recommendations »

Oct 11, 2018

Sep 21, 2018

Sep 19, 2018

Sep 6, 2018

Sep 4, 2018

Aug 16, 2018

Aug 14, 2018

Aug 8, 2018

Looking for more? Browse all our products here