Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of May 22, 2008
GAO-08-811T
Published: May 22, 2008. Publicly Released: May 22, 2008.
Skip to Highlights
Highlights
This testimony is based on our review of schedules and financial reports for the CVC project and related records maintained by AOC and its construction management contractor, Gilbane Building Company; our observations on the progress of work at the CVC construction site; and our discussions with the CVC team (AOC and its major CVC contractors) and AOC's Chief Fire Marshal. We also reviewed AOC's construction management contractor's periodic schedule assessments, proposed change order log, and weekly reports on construction progress.
Full Report
Office of Public Affairs
Topics
AccountabilityConstruction contractsContract administrationContract modificationsCost analysisCost overrunsFacility constructionFederal facilitiesFederal fundsFuture budget projectionsPublic visitor-centersRisk assessmentSchedule slippagesStrategic planningCost estimates