Capitol Visitor Center:
Update on Status of Project's Schedule and Cost as of June 27, 2007
GAO-07-897T: Published: Jun 27, 2007. Publicly Released: Jun 27, 2007.
Additional Materials:
- Full Report:
- Accessible Text:
Contact:
(202) 512-3000
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
The purpose of this testimony is to assist the Committees in monitoring progress on the Capitol Visitor Center (CVC) project. This testimony will focus on (1) the Architect of the Capitol's (AOC) construction progress since the last CVC hearing on April 24, 2007; and (2) the project's expected cost at completion and funding status. GAO's remarks are based on our review of schedules and financial reports for the CVC project and related records maintained by AOC and its construction management contractor, Gilbane Building Company; our observations on the progress of work at the CVC construction site; and our discussions with the CVC team (AOC and its major CVC contractors), AOC's Chief Fire Marshal, and representatives from the U.S. Capitol Police. We also reviewed AOC's construction management contractor's periodic schedule assessments, potential change order log, and weekly reports on the progress of interior wall and floor stonework. In addition, we reviewed the contract modifications made to date.
Since the April 24, 2007, CVC hearing, the project's construction has progressed, and AOC is still projecting a June 27, 2008, completion date. Although the CVC team has avoided further delays in the project's critical path (i.e., the work on the fire alarm system), activities on most of the project's near-critical paths have fallen behind schedule, and further delays are possible. During the past 2 months, the CVC team has made progress on the project's heating, ventilation, and air-conditioning (HVAC) system, interior wall stone and ceiling installation, and other interior and exterior construction work. However, problems have occurred in such near-critical activities as the ceiling close-ins in the upper level security and orientation lobbies and elements of the House and Senate expansion spaces, and a number of risks to the project's schedule remain. These include potential problems in completing the installation, integration, operation, and testing of complex, major building systems, including the fire alarm, security, and HVAC systems. For example, the subcontractor that is installing the fire alarm system told AOC in April that the installation may not proceed as scheduled because of cash flow issues and delays in other subcontractors' work. The subcontractor's cash flow issues are, in turn, related to another risk to the project's schedule--unsettled change order requests. Finally, a new risk emerged this month, when problems with the HVAC automated control system delayed the completion of efforts to test and balance of the HVAC units. Given these and other risks to the project's schedule, we believe that AOC will be able to meet or come close to meeting its scheduled construction completion date only if the CVC team promptly makes significant improvements in its execution of the project and the project's schedule. At the November 15, 2006, CVC hearing, we reported that the total cost of the entire CVC project at completion is likely to be about $592 million without an allowance for risks and uncertainties, and over $600 million with such an allowance. Because the project's expected completion date remains uncertain, we have not updated these estimates. To date, about $538.4 million has been approved for CVC construction, including about $7.4 million in fiscal year 2007 appropriations. For fiscal year 2007, AOC has also received an additional appropriation of $36.4 million for the CVC project, which AOC has not yet received approval to obligate. AOC has indicated that of this amount, approximately $23.8 million will be used for construction and $12.6 will be used for operations. AOC has also requested $20 million in fiscal year 2008 CVC construction appropriations to cover remaining costs, and we estimate that AOC may need further appropriations in future fiscal years for construction claims.
Jan 19, 2021
-
Federal Rulemaking:
Selected EPA and HHS Regulatory Analyses Met Several Best Practices, but CMS Should Take Steps to Strengthen Its AnalysesGAO-21-151: Published: Dec 17, 2020. Publicly Released: Jan 19, 2021.
Jan 13, 2021
-
Department of Energy Contracting:
Improvements Needed to Ensure DOE Assesses Its Full Range of Contracting Fraud RisksGAO-21-44: Published: Jan 13, 2021. Publicly Released: Jan 13, 2021.
Dec 16, 2020
-
Data Governance:
Agencies Made Progress in Establishing Governance, but Need to Address Key MilestonesGAO-21-152: Published: Dec 16, 2020. Publicly Released: Dec 16, 2020.
Dec 9, 2020
-
2020 Census:
The Bureau Concluded Field Work but Uncertainty about Data Quality, Accuracy, and Protection RemainsGAO-21-206R: Published: Dec 9, 2020. Publicly Released: Dec 9, 2020.
Dec 3, 2020
-
2020 Census:
Census Bureau Needs to Assess Data Quality Concerns Stemming from Recent Design ChangesGAO-21-142: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020. -
2020 Census:
Census Bureau Needs to Ensure Transparency over Data QualityGAO-21-262T: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020.
Nov 30, 2020
-
Federal Buying Power:
OMB Can Further Advance Category Management Initiative by Focusing on Requirements, Data, and TrainingGAO-21-40: Published: Nov 30, 2020. Publicly Released: Nov 30, 2020.
Nov 24, 2020
-
Disaster Response:
Agencies Should Assess Contracting Workforce Needs and Purchase Card Fraud RiskGAO-21-42: Published: Nov 24, 2020. Publicly Released: Nov 24, 2020.
Nov 23, 2020
-
Federal Contracting:
Actions Needed to Improve Department of Labor's Enforcement of Service Worker Wage ProtectionsGAO-21-11: Published: Oct 29, 2020. Publicly Released: Nov 23, 2020.
Nov 18, 2020
-
Federal Telework:
Key Practices That Can Help Ensure the Success of Telework ProgramsGAO-21-238T: Published: Nov 18, 2020. Publicly Released: Nov 18, 2020.
Looking for more? Browse all our products here