Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of April 17, 2007
Highlights
The purpose of this testimony is to assist the Committees in monitoring progress on the Capitol Visitor Center (CVC) project. This testimony will focus on (1) the Architect of the Capitol's (AOC) construction progress since the last CVC hearing on March 13, 2007; and (2) the project's expected cost at completion and funding status. GAO's remarks are based on our review of schedules and financial reports for the CVC project and related records maintained by AOC and its construction management contractor, Gilbane Building Company; observations on the progress of work at the CVC construction site; and discussions with the CVC team (AOC and its major CVC contractors), AOC's Chief Fire Marshal, and representatives from the U.S. Capitol Police.