DOE Contracting:
Better Performance Measures and Management Needed to Address Delays in Awarding Contracts
GAO-06-722: Published: Jun 30, 2006. Publicly Released: Aug 1, 2006.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Text:
Contact:
(202) 512-6870
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
The Department of Energy (DOE), the largest civilian contracting agency in the federal government, spends over 90 percent of its annual budget on contracts to operate its facilities and carry out its diverse missions. Federal law and regulations outline the steps DOE must follow in planning and carrying out the contract award process and emphasize the importance of awarding contracts in a timely manner. Several of DOE's recent contracts have taken much longer than anticipated to award. GAO was asked to determine (1) the extent to which DOE has experienced delays in awarding contracts and factors contributing to delays, (2) the impacts of any such delays, and (3) the extent to which DOE has taken steps to address the delays.
Delays in awarding DOE contracts occurred in most of the 31 contracts that GAO reviewed. In fiscal years 2002 through 2005, DOE awarded 131 contracts valued at $5 million or greater; the 31 of these contracts GAO reviewed were affiliated with DOE's three largest component organizations and represented about 73 percent of the dollars awarded. None of the 24 contracts awarded competitively was awarded by the date planned in DOE's schedule, with 23 of the contracts awarded between several weeks and 4-1/2 years later than the planned date. Of the 7 contracts awarded without competition, 6 were awarded on time or nearly so, with the remaining contract awarded 2 months late. Delays in awarding contracts occurred, in part, because DOE had to modify its approach after beginning the contract award process. At least some of the delays were avoidable, such as when DOE reworked contract awards to correct errors. Delays in awarding contracts could increase costs both to DOE and companies competing for DOE work. Because the department does not track its costs for awarding contracts, it was not feasible to quantify the impact of these delays. Companies competing for DOE's work may also face increased costs when contract awards are delayed, such as the costs associated with ensuring that key personnel identified in proposals continue to be available. Increased costs and delays may affect the willingness of companies to compete for future DOE work, although the actual impact is unknown. Until recently, DOE had not been addressing delays in awarding contracts because incomplete performance data indicated that most of the contracts were awarded in a timely manner. In late 2005, DOE began several efforts to improve its contract award process, including implementing improved measures of contract award timeliness and restructuring the Office of Environmental Management to strengthen management of the contracting process. However, two concerns could limit the effectiveness of these efforts: (1) the efforts do not encompass all of DOE's contract awards and (2) DOE does not have a systematic method of identifying and disseminating lessons learned and best practices from past or current contract awards.
Recommendations for Executive Action
Status: Closed - Implemented
Comments: DOE will continue to track and monitor the acquisition process for its facilities management and other critical contracts from planning to award. DOE plans to review its Balanced Scorecard measures and consider benchmarking those against other federal agencies as applicable.
Recommendation: To help ensure that DOE's contract award process for contracts that require a written plan and schedule is efficient and effective and that DOE is obtaining the best value for the government, the Secretary of Energy should ensure that performance measures for the timeliness of the department's contract awards include the entire contract award process from planning to contract award and include all of the department's contracts that require a written plan and schedule.
Agency Affected: Department of Energy
Status: Closed - Implemented
Comments: DOE's Office of Procurement and Assistance Management, as part of its fiscal year 2007 Balanced Scorecard initiative, proposes to determine if there are better ways to identify and disseminate lessons learned and best practices for the acquisition process.
Recommendation: To help ensure that DOE's contract award process for contracts that require a written plan and schedule is efficient and effective and that DOE is obtaining the best value for the government, the Secretary of Energy should establish a more systematic way of identifying lessons learned from past and current contract awards and sharing those lessons and best practices with the staff involved in planning and managing the department's efforts to award its contracts.
Agency Affected: Department of Energy
Explore the full database of GAO's Open Recommendations
»
Jan 13, 2021
-
Department of Energy Contracting:
Improvements Needed to Ensure DOE Assesses Its Full Range of Contracting Fraud RisksGAO-21-44: Published: Jan 13, 2021. Publicly Released: Jan 13, 2021.
Dec 16, 2020
-
Data Governance:
Agencies Made Progress in Establishing Governance, but Need to Address Key MilestonesGAO-21-152: Published: Dec 16, 2020. Publicly Released: Dec 16, 2020.
Dec 9, 2020
-
2020 Census:
The Bureau Concluded Field Work but Uncertainty about Data Quality, Accuracy, and Protection RemainsGAO-21-206R: Published: Dec 9, 2020. Publicly Released: Dec 9, 2020.
Dec 3, 2020
-
2020 Census:
Census Bureau Needs to Assess Data Quality Concerns Stemming from Recent Design ChangesGAO-21-142: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020. -
2020 Census:
Census Bureau Needs to Ensure Transparency over Data QualityGAO-21-262T: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020.
Nov 30, 2020
-
Federal Buying Power:
OMB Can Further Advance Category Management Initiative by Focusing on Requirements, Data, and TrainingGAO-21-40: Published: Nov 30, 2020. Publicly Released: Nov 30, 2020.
Nov 24, 2020
-
Disaster Response:
Agencies Should Assess Contracting Workforce Needs and Purchase Card Fraud RiskGAO-21-42: Published: Nov 24, 2020. Publicly Released: Nov 24, 2020.
Nov 23, 2020
-
Federal Contracting:
Actions Needed to Improve Department of Labor's Enforcement of Service Worker Wage ProtectionsGAO-21-11: Published: Oct 29, 2020. Publicly Released: Nov 23, 2020.
Nov 18, 2020
-
Federal Telework:
Key Practices That Can Help Ensure the Success of Telework ProgramsGAO-21-238T: Published: Nov 18, 2020. Publicly Released: Nov 18, 2020.
Oct 7, 2020
-
Unaccompanied Children:
Actions Needed to Improve Grant Application Reviews and Oversight of Care FacilitiesGAO-20-609: Published: Sep 15, 2020. Publicly Released: Oct 7, 2020.
Looking for more? Browse all our products here