National Science Foundation:
Status of the Business Analysis Plan Contract
GAO-03-832R: Published: Jul 10, 2003. Publicly Released: Jul 10, 2003.
Additional Materials:
- Full Report:
- Accessible Text:
Contact:
(202) 512-6246
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
In June 2002, the National Science Foundation (NSF) awarded a 3-year, $14.8 million contract for a business analysis plan to support three key management areas at the foundation: its business processes, human capital, and information technology. The contract is to be completed by September 30, 2005, and is to result in seven deliverables, including a project plan to guide the contractor's work. The Chairman, Senate Committee on Appropriations, Subcommittee on VA, HUD, and Independent Agencies, asked us to obtain information on (1) the status of contract funds budgeted to the key management areas and contract deliverables, and overall plans for the contract; (2) the extent to which the contract will address management issues previously reported by audit and oversight bodies; and (3) NSF's management of the contract and plans for integrating any recommendations made by the contractor.
As of May 31, 2003, NSF had spent about $1.9 million on the contract, with business processes and human capital management accounting for about 75 percent of the expenditures and information technology accounting for the remainder. Expenditure data by individual contract deliverable were unavailable because NSF did not estimate and is not tracking the costs of deliverables due from the contractor. NSF's current schedule for the contract reflects delays for early deliverables, including the first deliverable, the project plan. The contractor delivered a draft project plan to NSF on June 30, 2003, and NSF is working with the contractor to finalize it by July 15, 2003, over a year later than originally planned. Agency officials attributed delays of early deliverables primarily to funding limitations during fiscal year 2002 and the first half of fiscal year 2003. Despite the initial delays, NSF still expects the contract to be completed by its originally planned date. NSF plans to spend only the original base amount of the contract--$12.8 million--and does not have any current plans to use the additional $2 million it reserved for ad hoc analyses. The extent to which key management issues identified by audit and oversight bodies will be addressed under the contract is unknown. Over the past few years, audit and oversight bodies such as GAO, the Office of Management and Budget, and NSF's Office of the Inspector General have reported on various management issues at NSF, including issues related to budget performance, financial management, human capital, information technology, and award and project management. NSF's initial contract documents, such as its statement of work and request for proposals, contained provisions for the majority of these management issues to be included in the scope of the contract. The awarded contract requires the contractor to perform early survey work to determine the specific issues to address within the contract deliverables. Therefore, until the survey work and project plan are completed, the extent to which the key management issues will be addressed under the contract is unknown. Before and since the award of the contract, NSF contract management staff has kept senior-level officials apprised, through periodic briefings, of its plans for and progress on the contract. Some of these organizations also have provided advice and guidance on the contract. For example, the Business and Operations Advisory Committee encouraged the business analysis team to consider, among other things, how other government-wide efforts, such as enterprise architecture, might affect its work and recommendations. In addition, the committee encouraged the team to coordinate with other ongoing work at NSF that might have implications for the business analysis plan. Also, in the early stages of contract development, the Office of the Inspector General encouraged strong oversight of the contractor by NSF. To implement any recommendations resulting from the contract, NSF plans to work the recommendations through its normal chain of command.
Sep 25, 2020
-
Whistleblower Protection:
Actions Needed to Strengthen Selected Intelligence Community Offices of Inspector General ProgramsGAO-20-699: Published: Sep 25, 2020. Publicly Released: Sep 25, 2020.
Sep 23, 2020
-
Federal Property:
Formal Policies Could Enhance FDA's Property Management EffortsGAO-20-689: Published: Sep 23, 2020. Publicly Released: Sep 23, 2020.
Sep 10, 2020
-
2020 Census:
Key Areas for Attention Raised by Compressed TimeframesGAO-20-720T: Published: Sep 10, 2020. Publicly Released: Sep 10, 2020. -
Federal Advisory Committees:
Actions Needed to Enhance Decision-Making Transparency and Cost Data AccuracyGAO-20-575: Published: Sep 10, 2020. Publicly Released: Sep 10, 2020. -
Grants Management:
Agencies Provided Many Types of Technical Assistance and Applied Recipients' FeedbackGAO-20-580: Published: Aug 11, 2020. Publicly Released: Sep 10, 2020.
Sep 8, 2020
-
Federalism:
Opportunities Exist to Improve Coordination and Consultation with State and Local GovernmentsGAO-20-560: Published: Aug 7, 2020. Publicly Released: Sep 8, 2020.
Aug 31, 2020
-
Time and Attendance:
Agencies Generally Compiled Data on Misconduct, and Reported Using Various Internal Controls for MonitoringGAO-20-640: Published: Aug 31, 2020. Publicly Released: Aug 31, 2020.
Aug 27, 2020
-
2020 Census:
Recent Decision to Compress Census Timeframes Poses Additional Risks to an Accurate CountGAO-20-671R: Published: Aug 27, 2020. Publicly Released: Aug 27, 2020.
Aug 19, 2020
-
Interagency Council on Homelessness:
Governance Responsibilities Need Further ClarificationGAO-20-602: Published: Aug 19, 2020. Publicly Released: Aug 19, 2020.
Jul 9, 2020
-
DATA Act:
OIGs Reported That Quality of Agency-Submitted Data Varied, and Most Recommended ImprovementsGAO-20-540: Published: Jul 9, 2020. Publicly Released: Jul 9, 2020.
Looking for more? Browse all our products here

Explore our Key Issues on Government Operations