[Protest of Proposed GSA Contract Award]

B-270532 Published: Nov 17, 1995. Publicly Released: Nov 17, 1995.
Jump To:
Skip to Highlights

Highlights

A firm protested a proposed General Services Administration (GSA) contract award, contending that GSA should have rejected the awardee's bid as nonresponsive, since the awardee failed to meet a solicitation requirement. GAO held that the awardee's failure to meet the site inspection requirement was not a valid basis to reject its otherwise responsive bid. Accordingly, the protest was dismissed.

Office of Public Affairs

Topics

Bid evaluation protestsBid responsivenessBuilding inspectionFederal procurementSolicitation specifications