[Protest of DRMS Rejection of Bid]

B-260081 Published: Feb 22, 1995. Publicly Released: Feb 22, 1995.
Jump To:
Skip to Highlights

Highlights

A firm protested the Defense Reutilization and Marketing Service's rejection of its late bid, contending that: (1) its bid was received 4 days after bid opening due to a post office error; and (2) the decision to reject its late bid was not in accordance with the terms of the solicitation. GAO held that: (1) the protester was responsible for ensuring that its bid arrived at the designated location at the designated time; (2) bids that do not arrive on time generally are not accepted; and (3) the rejection of the protester's late bid was not legally objectionable. Accordingly, the protest was dismissed.

Office of Public Affairs

Topics

Bid rejection protestsDefense procurementLate bidsMail delivery problemsOffer acceptance periodsPostal service