[Protest of Navy Rejection of Bid]

B-257706 Published: Jul 14, 1994. Publicly Released: Jul 14, 1994.
Jump To:
Skip to Highlights

Highlights

A firm protested the Navy's rejection of its bid, contending that the Navy improperly rejected its bid for failure to submit a bond in the required amount. GAO held that the: (1) protester untimely filed after bid opening its protest of the bonding requirement; and (2) Navy properly rejected the protester's bid as nonresponsive, since its bid bond was inadequate. Accordingly, the protest was dismissed.

Office of Public Affairs

Topics

Bid bondsBid guaranteesBid rejection protestsBid responsivenessNaval procurementSpecifications protestsUntimely protestsU.S. NavyBid evaluation protestsFederal acquisition regulationsIntellectual property rightsReprocurementFederal regulationsPerformance bonds