[Protest of GSA Contract Award]

B-256596: Apr 8, 1994

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested a General Services Administration (GSA) contract award, contending that GSA improperly issued the solicitation on a sole-source basis. GAO held that the protester untimely filed after bid opening its protest against alleged solicitation improprieties. Accordingly, the protest was dismissed.

Oct 29, 2020

Oct 28, 2020

Oct 27, 2020

  • Silver Investments, Inc.
    We dismiss the protest as untimely because it was filed more than 10 days after the protester knew, or should have known, the basis for its protest.