B-230873, Nov 21, 1988

B-230873: Nov 21, 1988

PROCUREMENT - Contract Disputes - Shipment costs - Freight charges DIGEST: Where a carrier's tender supplement that was in effect when a particular shipment moved provided that "shipments accorded exclusive use-of-vehicle service" will be "rated" under an identified rate table. The intent of the supplement was to combine rate factors for both line haul and exclusive- use services into one charge....

  • html report icon View Decision (HTML)
[Request for Review of GSA Denial of Carrier's Claim for Additional Vehicle Charges]

B-230873: Nov 21, 1988

A carrier requested a review of the General Services Administration's (GSA) denial of its claim for a supplemental bill for exclusive-use charges, contending that the charges were allowable under the tender in effect when it moved the shipment. GAO held that the carrier: (1) transported the shipment before the tender's effective date; and (2) had already rated its exclusive-use shipment on the app...

  • pdf icon View Decision (PDF, 3 pages)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap