[Protest of Air Force Contract Award for Aircraft Forward Transparencies]

B-258600.2 Published: Apr 20, 1995. Publicly Released: Apr 20, 1995.
Jump To:
Skip to Highlights

Highlights

A firm protested an Air Force contract award for aircraft forward transparencies, contending that the Air Force improperly denied it the award on the basis that it had not completed a flight test that should not be performed until after award. GAO held that the: (1) contract award was limited to approved sources; (2) solicitation clearly stated that the flight test was required for source approval; and (3) Air Force gave the protester a reasonable opportunity to become an approved source. Accordingly, the protest was denied.

Office of Public Affairs

Topics

Air Force procurementAircraft componentsContract award protestsEquipment contractsLimited procurementQualified bidders listTechnical proposal evaluationTestingOperational testingEngineeringBid evaluation protestsU.S. Air Force