[Protest of NASA Contract Award for Construction Support]

B-255178,B-255178.2 Published: Feb 14, 1994. Publicly Released: Feb 14, 1994.
Jump To:
Skip to Highlights

Highlights

A firm protested a National Aeronautics and Space Administration (NASA) contract award for construction support, contending that NASA: (1) engaged in technical levelling with the awardee; and (2) performed an inadequate cost analysis. GAO held that NASA: (1) did not engage in technical levelling, since it requested only one round of best and final offers; and (2) performed a reasonable cost analysis of the awardee's bid. Accordingly, the protest was denied.