[Request for Reconsideration of Protest of Navy Solicitation]

B-249069.2 Published: Nov 09, 1992. Publicly Released: Nov 09, 1992.
Jump To:
Skip to Highlights

Highlights

A firm requested reconsideration of the dismissal of its protest of a Navy solicitation for radar display units. GAO had held that the protester untimely filed its protest of the Navy's linkage of its pricing under a letter contract to its pricing under a competitive procurement. In its request for reconsideration, the protester contended that: (1) it was not required to protest before the closing date for receipt of final offers; and (2) GAO should consider its protest under the significant-issue exception to timeliness rules. GAO held that the protest: (1) was untimely; and (2) did not present significant issues. Accordingly, the request for reconsideration was denied.

Office of Public Affairs

Topics

Bid protest regulationsEquipment contractsNaval procurementReconsideration requests deniedSpecifications protestsUntimely protestsBid evaluation protestsU.S. Navy