[Protest of Navy Contract Award for Air Compressors]

B-241498.2 Published: Dec 05, 1991. Publicly Released: Dec 05, 1991.
Jump To:
Skip to Highlights

Highlights

A firm protested a Navy contract award for air compressors, contending that, in response to a GAO recommendation, the Navy improperly determined that the protester's alternative technology was unacceptable. GAO held that the protester untimely filed its protest more than 10 days after it knew the basis for protest. Accordingly, the protest was dismissed.

Office of Public Affairs

Topics

Bid evaluation protestsContract award protestsContract terminationEquipment contractsNaval procurementUntimely protests