[Protest of Navy Contract Award for Command/Control System Laboratory]
B-236170: Aug 11, 1989
Additional Materials:
- Full Report:
Contact:
A firm protested a Navy contract award for a command/control system laboratory, contending that the Navy improperly rejected its low bid on the basis of its sureties' unacceptability. GAO would not review the protest, which the protester untimely filed more than 10 working days after it became aware of the protest basis. Accordingly, the protest was dismissed.
Oct 26, 2020
-
Chronos Solutions, LLC; Inside Realty, LLC; BLB Resources, Inc.
We sustain the protests.
B-417870.2,B-417870.3,B-417870.4 -
-
Oct 23, 2020
Oct 22, 2020
Oct 20, 2020
Oct 16, 2020