[Protest of Navy Rejection of Bid as Nonresponsible]
B-222526
Published: Jul 25, 1986. Publicly Released: Jul 25, 1986.
Skip to Highlights
Highlights
A firm protested its rejection as a nonresponsible bidder under a Navy solicitation, contending that it had completed guaranteed work on a previous contract before bid opening. GAO held that: (1) one of the protester's sureties failed to disclose its obligations under the other contract; and (2) the Navy properly rejected the bid. Accordingly, the protest was denied.
Full Report
Office of Public Affairs
Topics
Bid bondsBid rejection protestsBidder responsibilityNaval procurementSmall business set-asidesU.S. NavySmall businessBid evaluation protestsSolicitationsPerformance bonds