[Request for Reconsideration of Dismissed Bid Rejection Protest]

B-222806.3 Published: May 09, 1986. Publicly Released: May 09, 1986.
Jump To:
Skip to Highlights

Highlights

A firm requested reconsideration of the dismissal of its protest under an Army prime contractor's solicitation for demolition charges, contending that the specification deviations it requested were insignificant and questioning the contractor's decision to reject its bid as nonresponsive. GAO found that: (1) the contractor's decision was reasonable because the protester had conditioned its performance on approval of the requested deviations; and (2) the protester offered no evidence of error in the original decision. Accordingly, the original decision was affirmed.

Full Report

Office of Public Affairs

Topics

Army procurementBid protest reconsiderationsBid rejection protestsBid responsivenessContract award protestsSolicitation specifications waiversBid evaluation protestsU.S. ArmyEngineeringDemolitionMunitionsIntellectual property rightsSealed biddingAmmunition