The protester requested reconsideration of a decision in which GAO declined to reconsider its protest concerning an agency determination that a less restrictive solicitation would meet the Government's needs. GAO reaffirmed its policy not to consider this matter under its bid protest functions. The dispute was one for resolution between the using and the procuring activities, and was inappropriate for review by GAO.