Skip to main content

PTC Inc.

Skip to Highlights

Highlights

PTC, Inc., of Needham, Massachusetts, challenges a notice of intent to award a sole-source contract to Siemens Government Technologies, Inc., of Arlington, Virginia, issued by the Department of the Air Force for product lifecycle management (PLM) software. The protester alleges that the agency's justification and approval (J&A) supporting the proposed sole-source contract is not consistent with the cited regulatory authority, and is based on a flawed cost analysis.

We deny the protest.

We deny the protest.
View Decision