STR, L.L.C.
Highlights
STR, L.L.C. protests the proposed award of a subcontract by SRA International, Inc., a government prime contractor, to Infoterra, Inc. The subcontract is for a grants management software program to be used by the Agency for International Development (AID) and the Department of State.
B-297421, STR, L.L.C., December 22, 2005
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release.
Thomas A. Coulter, Esq., LeClair Ryan P.C., for the protester.
Warren D. Leishman, Esq., and Peter E. Young, Esq., Agency for International Development, for the agency.
Jennifer D. Westfall-McGrail, Esq., and Christine S. Melody, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Government Accountability Office will not consider protest of an award of a subcontract as by the government where the prime contractor drafted the portion of the solicitation pertaining to evaluation of vendor responses; participated substantially in the evaluation of responses and selection of a product for award; and will be responsible for administration of the subcontract.
DECISION
STR, L.L.C. protests the proposed award of a subcontract by SRA International, Inc., a government prime contractor, to Infoterra, Inc. The subcontract is for a grants management software program to be used by the Agency for International Development (AID) and the Department of State.
SRA holds a contract with the General Services Administration (GSA) Federal Systems Integration and
SRA's issuance of the RFI at issue here was preceded by AID's issuance, and subsequent withdrawal, of an RFI seeking related information regarding commercially available acquisition and assistance systems. The AID RFI differed from the SRA RFI in several respects, one of which was that it notified vendors that the agencies were soliciting vendor responses for market research purposes only and that the RFI would not result in a contract award. In keeping with the foregoing, the AID RFI did not contain evaluation criteria, whereas the SRA solicitation did.
STR submitted responses to both RFIs. On October 3, SRA notified STR that its product had not been selected; in a subsequent telephone conversation, SRA informed STR that the selected vendor was Infoterra.
The protester takes issue with the selection of Infoterra, arguing that the firm does not have a full system in production in any federal agency, as required by the RFI.
We will not consider the merits of STR's arguments because, as explained below, the procurement at issue was not conducted by or for a federal agency and thus is not subject to our jurisdiction.
Under the Competition in Contracting Act of 1984 (CICA), our Office has jurisdiction to resolve bid protests concerning solicitations and contract awards that are issued by a Federal agency. 31 U.S.C. sect. 3551(1)(A) (2000). Pursuant to our authority under CICA, we initially took jurisdiction over subcontract awards by prime contractors to the federal government where, as result of the government's involvement in the award process, or the contractual relationship between the prime contractor and the government, the subcontract in effect was awarded on behalf of--i.e., by or for--the government, and federal procurement laws and regulations otherwise would apply. See, e.g., St. Mary's Hosp. and Med. Ctr. of
We continue to take jurisdiction where the subcontract is by the government. RGB Display Corp., B-284699,
STR contends that SRA is acting merely as a conduit for the government here and that, accordingly, we should take jurisdiction over its protest.[2]
We do not agree with the protester that the government's involvement in and control over the acquisition process here was so pervasive as to render the procurement essentially by the government. First, contrary to STR's contention, the RFI issued by SRA is not nearly identical to the solicitation issued by AID; as noted above, the two differ significantly in that the AID RFI did not include evaluation criteria, whereas the SRA solicitation did. Both the AID program manager and the SRA project manager report that SRA had primary responsibility for drafting the evaluation criteria.[3]
Second, it is clear from the record that SRA personnel played a major role in the evaluation of proposals and selection of an awardee. In this connection, the evaluation team consisted of both government representatives and SRA employees, with the two subgroups providing differing types of substantive input into the evaluation/selection process. As explained by the AID program manager in the following excerpt:
The government team members represented various user stakeholders of the COTS system to include grants officers, program officers, financial analyst, policy analyst, and IT analyst. These representatives focused primarily on the requirements and the ability of the software to meet them from a users' perspective, e.g., ease of use, intuitiveness, logical flow. Concurrently, SRA conducted in-depth technical and cost assessments and performed customer reference interviews. SRA analysis, from the integration perspective, included requirements, technical feasibility, implementation factors to configure the system, and the complexity of the integration points of the software from a risk and schedule impacts.
Declaration of AID Program Manager,
Third, it is apparent from the record that administration of the contract is to be handled by SRA and that privity of contract will be between the SRA and Infoterra and not between the government and Infoterra. Declaration of AID Program Manager,
Because we find that the procurement here was not by the government, we conclude that we do not have jurisdiction over STR's protest. Accordingly, the protest is dismissed.
Anthony H. Gamboa
General Counsel
[1] AID has not requested that we review protests of the award of subcontracts by its prime contractors.
[2] In its initial protest, STR also argued that SRA meets the definition of procurement agent set forth in
[3] The AID program manager stated as follows:
The SRA team managed the second RFI process to include the drafting of the document . . . The contents of the RFI document, to include the instructions and evaluation criteria was drafted using SRA's standard commercial practices for recommending COTS solutions. The government reviewed and concurred to the final draft of the RFI prior to issuance.
Declaration of AID Program Manager,
[4] Similarly, the SRA project manager stated as follows:
SRA had full responsibility, as part of its performance based contract, for assessing the technical merits of the competing programs and the ease of integrating each program into the overall JAMS system and USAID architecture.
Declaration of SRA Project Manager,