Matter of: Telex Communications, Inc. File: B-287146 Date: April 25, 2001

Skip to Highlights

Highlights

DIGEST Rejection of protester's proposal is unobjectionable where required product sample was received by contracting agency after the time stated in the solicitation. Although the protester argues that the agency failed to properly address the sample request so that the request was allegedly misdirected. Although the text of the protester's proposal was received by the proposal due date. The required product sample was not submitted by the time established in the RFP. Telex contends that actions by the agency were the paramount cause for the late delivery of its product sample. The successful contractors under the RFP will provide various types of hearing aids for all VA medical facilities and other government agencies worldwide.

View Decision

GAO Contacts

Shirley A. Jones
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries