[Protest of Air Force Contract Award for Technical Assistance]
B-279622
Published: Jul 02, 1998. Publicly Released: Jul 02, 1998.
Skip to Highlights
Highlights
A firm protested an Air Force contract award for total systems performance responsibility, contending that the Air Force's decision to award a sole-source contract was unreasonable. GAO held that the Air Force reasonably determined that only one source could complete the contract within the urgent time constraints of the procurement. Accordingly, the protest was denied.