Skip to main content

Matter of: Beldon Roofing & Remodeling Company File: B-277651 Date: November 7, 1997

Skip to Highlights

Highlights

DIGEST A solicitation for a requirements contract should be canceled and resolicited where the contracting agency cannot establish that the solicitation's quantity estimates are realistic and reflect the government's actual anticipated requirements. Beldon argues that its bid is not unbalanced. Beldon argues that the IFB is flawed since the quantity estimates in the solicitation do not reasonably reflect the government's needs. We agree with Beldon that the solicitation is flawed and we sustain the protest on that basis. Along with an estimated quantity for each CLIN. [1] Bidders were to supply a unit price for each CLIN. Which was to be multiplied by the estimated quantity to determine an extended price for that CLIN.

View Decision

GAO Contacts

Shirley A. Jones
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries