[Former PCC Employee's Liability for Unnecessary Contract Payments]

Skip to Highlights

Highlights

A former Panama Canal Commission (PCC) employee contested the validity of his indebtedness for $88,040 in unnecessary contract payments for liquid chlorine. GAO held that PCC: (1) reasonably assessed liability against the former employee for the unnecessary contract payments, since he failed to conduct a market price survey as required by federal acquisition regulations; and (2) followed applicable regulations in administering the offset against the former employee's final compensation and retirement account.

View Decision