Matter of: Holmes Brothers Enterprises, Inc. File: B-255271 Date: February 23, 1994

Skip to Highlights

Highlights

Protest that an agency decision to delete critical work items from request for proposals for ship repairs after receipt of initial proposals and to direct that those items be performed in-house was an attempt to improperly circumvent the Small Business Act's certificate of competency procedures is denied where the contracting officer reasonably determined that by removing the critical work items. Were afforded an opportunity to submit offers based on the revised solicitation. Offerors were required to submit a lump sum price for the basic requirement. Award was to be made to the offeror whose proposal was most advantageous to the government. The preaward survey team concluded that Holmes was not a responsible contractor to perform this effort and recommended that the firm not be awarded the contract.

View Decision

GAO Contacts

Shirley A. Jones
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries