Matter of: Vista Contracting, Inc. File: B-255267 Date: January 7, 1994

Skip to Highlights

Highlights

Thus bidder's total price offer is easily determinable from the face of its bid documents. Is otherwise properly executed. Where the cumulative bid price is ascertainable from the face of the submitted bid pricing schedule. Fact that bidder indicated bid bond indemnification amount as a percentage rather than exact numerical amount does not require rejection of bid as nonresponsive since the surety is clearly bound to indemnify the government in the required amount. Vista contends that PEI's bid should have been rejected as nonresponsive since the awardee failed to insert a total bid price in the appropriate block of its bid cover sheet. Bidders were to complete and submit a pricing schedule.