Matter of: Moore Heating & Plumbing, Inc. File: B-254024 Date: November 16, 1993

Skip to Highlights

Highlights

PROCUREMENT Specifications Minimum needs standards Competitive restrictions Design specifications Justification Protest that agency's drawings and specifications for an underground piping system are unreasonable and overly restrictive. Is denied where the agency's system configuration requirements. Are designed to achieve a long. The protested drawings and specifications are for the replacement of approximately 5. UHDS projects are often procured on a "systems approach."[1] Under this approach. Soil classification and bidders are required to provide prequalified systems.[2] In this IFB. The project drawings and specifications are based upon certain characteristics of the system that is being replaced.

View Decision

GAO Contacts

Shirley A. Jones
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries