Matter of: Haworth, Inc. File: B-252826; B-252831 Date: July 29, 1993

B-252826,B-252831 Jul 29, 1993
Skip to Highlights

Highlights

PROCUREMENT Special Procurement Methods/Categories Federal supply schedule Purchases Cost/technical tradeoffs Technical superiority Award to higher priced vendor under the Federal Supply Schedule was not improper where agency obtained two other quotations for schedule vendors but determined that neither vendor offered a product that met the agency's minimum needs for compatibility with existing furniture. The contract specialists to whom the requests were assigned verified Herman Miller's prices from the Federal Supply Schedule (FSS) and requested quotations from two local representatives of two other firms with FSS contracts for systems furniture. That inclusion on the FSS represents a conclusive determination that a contractor will meet minimum requirements for any order under the schedule.

View Decision

GAO Contacts

Shirley A. Jones
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries