Matter of: AAA Engineering & Drafting, Inc. File: B-250323 Date: January 26, 1993

Skip to Highlights

Highlights

Reject an offer that was otherwise in line for award without inquiring of the offeror as to the intent and meaning of the information. Where the import and the meaning of the information is not clear. The successful contractor under the RFP is required to furnish the labor. Technical evaluation criteria were set forth as follows: (a) Technical Approach (b) Manning (c) Organization (d) Personnel Qualification (e) Implementation Plan (f) Offeror's Management and Operational Experience The solicitation explained that with regard to the "manning" technical evaluation criterion the offers would "be evaluated on allocation and management of resources.". That a minimum of [DELETED] employees was necessary to perform the requirements of the SOW.

View Decision

GAO Contacts

Shirley A. Jones
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries