[Protest of BOP Rejection of Bid for Sprinkler System]

B-245525 Published: Sep 24, 1991. Publicly Released: Sep 24, 1991.
Jump To:
Skip to Highlights

Highlights

A firm protested the Bureau of Prison's (BOP) rejection of its bid as nonresponsive for sprinkler system installation, contending that its failure to sign the certificate of procurement integrity was a waivable minor informality. GAO held that BOP properly rejected the protester's bid as nonresponsive, since the protester's failure to complete the certificate was a material deficiency. Accordingly, the protest was dismissed.