Skip to main content

[Protest of DGSC Contract Award for Watches]

B-242568 Published: May 13, 1991. Publicly Released: May 13, 1991.
Jump To:
Skip to Highlights

Highlights

A firm protested a Defense General Supply Center (DGSC) contract award for watches, contending that the awardee's proposal did not comply with a jewel-bearing requirement. GAO held that the awardee's bid stated that it would not comply with the requirements. Accordingly, the protest was sustained, and GAO recommended that DGSC reimburse the protester for its bid and protest preparation costs.

Full Report

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries