Skip to main content

[Protest of Coast Guard Rejection of Late Bid for Ship Repairs]

B-240301 Oct 30, 1990
Jump To:
Skip to Highlights

Highlights

A firm protested the Coast Guard's rejection its late bid for ship repairs, contending that the Coast Guard: (1) failed to promptly deliver its bid to the appropriate location after receipt in the mailroom; (2) failed to return its phone call to confirm receipt of the bid; and (3) should consider its bid, since only one timely bid was received. GAO held that the: (1) protester was solely responsible for ensuring the timely arrival of its bid at the appropriate location; (2) Coast Guard was not responsible for informing the protester of its bid's arrival; and (3) fact that the protester's bid was allegedly lower than the awardee's did not establish the awardee's price as unreasonable. Accordingly, the protest was denied.

View Decision

B-240301, Oct 30, 1990, 90-2 CPD ***

PROCUREMENT - Sealed Bidding - Bids - Late submission - Rejection - Propriety DIGEST: 1. Where bidder sent bid by U.S. Postal Service Express Mail only 1 working day before bid opening; bid arrived at government installation only approximately 6 hours before bid opening; and installation's normal mail delivery procedures would not have assured timely delivery to bid opening room, reason for late receipt of bid in bid opening room was bidder's failure to allow sufficient time for delivery, not government mishandling; accordingly, the bid was properly rejected as late. 2. Late bid may not be considered on ground that agency failed to respond to protester's inquiry confirming whether agency received its bid before bid opening; agency does not have a duty to inform protester about arrival of its bid. PROCUREMENT - Bid Protests - Competition - Adequacy 3. Competition was adequate, even where only one bid is timely received, where there is no evidence or allegation that the bid price was unreasonable, since all interested firms had opportunity to compete, and bid was submitted under threat of competition.

Attorneys

Bay Shipbuilding Corporation:

Bay Shipbuilding Corporation protests the Coast Guard's rejection of its bid as late under invitation for bids (IFB) No. DTCG80-90-B-100127, for the dockside repair of the Coast Guard Cutter Mackinaw. The bid was rejected because it was not received at the bid opening room until the morning after the scheduled opening.

We deny the protest.

The IFB required that bids be received in a specified room by 2 p.m., Monday, June 25, 1990. Bay submitted its properly addressed bid package to the U.S. Postal Service for Express Mail delivery on Friday, June 22. The Postal Service attempted to deliver Bay's bid package on Saturday, June 23 but was unable to do so since the installation's mail room is not open on Saturdays. The Postal Service was able to deliver the bid on Monday, June 25, the bid opening date, at 7:45 a.m. A mailroom employee signed for the Express Mail package and placed it in a box to be picked up
by personnel from the procurement office designated on the package label.
On the same day, at 11:30 a.m., Bay called the agency and left a message
requesting confirmation that its bid had timely arrived at the bid opening
room, but the agency did not return the call.
The Coast Guard reports
that the normal delivery procedure for Express Mail received at the
installation's mailroom is designed to result in delivery to the office
designated on the envelope between 1 p.m. and 2:30 p.m. on the day it
arrives in the mailroom.

Bid opening occurred on June 25 as scheduled.
Only one bid was received,
from Merce Industries, at $1,175,104.
Bay's bid package was not delivered
to the bid opening room until 9:37 a.m. on June 26.
Bay's bid was
therefore rejected as late.
(The agency has not opened the bid but Bay
states that it was $344,512 lower than Merce's bid.)

Bay contends that the cause for late receipt of its bid at the bid
opening room was mishandling by the Coast Guard and that its bid should
therefore be considered for award.
Specifically, Bay argues that if the
agency had followed its normal Express Mail procedures in delivering Bay's
bid to the room designated on the bid package, Bay's bid may have been
delivered by the 2 p.m. bid opening deadline.
In Bay's view, mishandling
is clearly evidenced by the fact that the bid ultimately was delivered to
the opening room 26 hours after receipt in the mailroom, clearly contrary
to normal delivery procedures.

A bid received in the office designated for the receipt of bids after the
time set for bid opening is a late bid.
Federal Acquisition Regulation
(FAR) Sec. 14.304-1.
Late mailed bids received before award are proper
for consideration where it can be determined that the late receipt was due
solely to mishandling by the government after receipt at the government
installation.
FAR Sec. 14.304-1(a)(2); see West End Welding and
Fabricating, B-225427, Dec. 31, 1986, 86-2 CPD Para. 724.
However,
bidders must allow a reasonable time for bids to be delivered from the
point of receipt to the location designated for receipt of bids; when they
do not do so, late arrival at the designated location cannot be attributed
to government mishandling.
Weather Data Servs., Inc., B-238970, June 22,
1990, 90-1 CPD Para. 582.

Mishandling was not the cause of the lateness of Bay's bid.
Although the
Coast Guard had an established Express Mail procedure which ordinarily
would provide for prompt delivery after receipt in the mailroom, and it is
not clear why Bay's package was not delivered promptly, this procedure is
not designed to assure delivery of packages by 2 p.m. on the day of
receipt in the mailroom.
Rather, the procedure only provides for delivery
between 1 and 2:30 p.m. Accordingly, even if Bay's bid had been delivered
to the bid opening room on June 25, the same day it arrived in the
mailroom, it still might not have been received in the bid opening room
prior to bid opening.

The lateness of Bay's bid clearly is attributable to the fact that the
bid was not delivered to the government installation until the day of bid
opening.
It is fundamental that bidders are solely responsible for
ensuring the timely arrival of their bids and must bear the responsibility
for late arrival.
Goodwin Contractors, B-228336, Dec. 17, 1987, 87-2 CPD
Para. 604.
By waiting until 1 government working day prior to bid opening
to mail its bid, Bay accepted the risk that upon arrival the
installation's delivery procedures would not guarantee delivery prior to
the 2 p.m. bid opening on the next business day.
This risk did not shift
to the government by virtue of the presence of a delivery procedure that
might have resulted in timely delivery of its bid.
In fact, it does not
appear that Bay relied on the installation's Express Mail delivery
procedure; Bay's protest does not indicate that it was even aware of the
procedure when it engaged the Postal Service to deliver its bid only 1
working day before bid opening (Friday, June 22).
/1/

Bay contends that by failing to return Bay's phone call before 2 p.m. to
inform Bay that its bid had not yet arrived in the bid opening room, the
agency did not take any steps to ensure timely arrival of Bay's bid, and
thereby failed to ensure full and open competition.
However, there is no
duty on the part of an agency to inform a bidder about the arrival of its
bid, and a contracting officer's failure to respond to an inquiry about a
bid's arrival therefore is not a ground for consideration of a late bid.
Goodwin Contractors, B-228336, supra.

Bay maintains that the Coast Guard should consider its bid for award in
any case, since only one timely bid was received.
However, there can be
adequate competition even where only one reasonably priced bid is received
under the threat of competition.
Survivair div. of U.S.D. Corp.,
B-215214, Dec. 3, 1984, 84-2 CPD Para. 600.
The mere fact that Bay's
price
was lower than Merce's does not establish that Merce's price was unreason-
able, and the agency apparently considers Merce's price reasonable.

The protest is denied.

/1/ The protester has neither stated nor provided evidence that the Express Mail package was marked as containing a bid or that it indicated the bid opening time. In the absence of such information, mailroom personnel had no reason to expedite delivery of Bay's bid to meet the 2 p.m. bid opening deadline.










Downloads

GAO Contacts

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries