B-238460, Feb 8, 1990, 90-1 CPD 166

B-238460 Feb 08, 1990
Jump To:
Skip to Highlights

Highlights

PROCUREMENT - Bid Protests - GAO procedures - Protest timeliness - 10 day rule DIGEST: Protest filed more than 10 days after protester was orally informed that its agency-level protest had been denied is untimely. McCullough challenges the contracting officer's determination that the protester's proposed individual sureties are nonresponsible. The protester was the apparent low bidder. Notified McCullough that its bid was ineligible for award because its individual sureties were determined to be unacceptable. Informed it that the individual sureties proposed were unacceptable and that the contracting officer was still abiding by his decision. As we have indicated. Where a protest initially was filed with the contracting agency.

View Decision

B-238460, Feb 8, 1990, 90-1 CPD 166

PROCUREMENT - Bid Protests - GAO procedures - Protest timeliness - 10 day rule DIGEST: Protest filed more than 10 days after protester was orally informed that its agency-level protest had been denied is untimely; protester may not delay filing its protest until it has received the agency decision in writing.

Attorneys

W. D. McCullough Construction Company and M A Equipment and Constructors Inc., a joint venture:

The joint venture of W. D. McCullough Construction Company and M A Equipment and Constructors Inc. (McCullough), protests its rejection as nonresponsible under invitation for bids (IFB) No. DACW56-90-B-0003, issued by the Department of the Army for embankment rehabilitation of Wister Lake, Poteau River, Oklahoma. McCullough challenges the contracting officer's determination that the protester's proposed individual sureties are nonresponsible.

We dismiss the protest.

The protester has provided us with a chronology of events and correspondence which preceded the filing of the protest. From this, it appears that at bid opening on November 21, 1989, the protester was the apparent low bidder. On November 25, the contracting activity requested additional supporting information concerning the existence of the joint venture and the financial capacity of the proposed individual sureties. After McCullough forwarded some information, the contracting officer reviewed it, and on December 10, notified McCullough that its bid was ineligible for award because its individual sureties were determined to be unacceptable. McCullough filed a written protest at the contracting activity on December 10, challenging the nonresponsibility determination. /1/ The contracting officer met with the protester on December 15, and informed it that the individual sureties proposed were unacceptable and that the contracting officer was still abiding by his decision. By a letter dated December 22, the contracting officer confirmed his December 15 denial of McCullough's protest.

On January 31, McCullough filed a protest in our Office alleging that the contracting officer had improperly rejected its proposed individual sureties.

As we have indicated, under our Bid Protest Regulations, where a protest initially was filed with the contracting agency, a subsequent protest to our Office must be filed within 10 working days after the protester learned of adverse action at the agency level. 4 C.F.R. Sec. 21.2. have expressly held that oral notification of the contracting agency's denial of the protest filed with it starts the 10-day period running, Harbour Air, Inc., B-235534.2, July 27, 1989, 89-2 CPD Para. 86; dismissal aff'd, Harbour Air, Inc.-- Request for Reconsideration, B-235534.3, Aug. 31, 1989, 89-2 CPD Para. 201, and that a protester may not delay filing its protest until it has received the agency's position in writing. Id. Moreover, once informed of initial adverse agency action, a protester may not delay filing a protest within our Office while it continues to discuss the matter with the agency. Midwest CATV-- Request for Reconsideration, B-233105.4, July 20, 1989, 89-2 CPD 64.

Since McCullough was informed on December 15 of the contracting officer's denial, its protest challenging that determination filed with us approximately 6 weeks later is untimely.

The protest is dismissed.

/1/ On December 14, McCullough addressed a second letter of protest to the contracting officer, a copy of which it sent to our Seattle Regional Office, which forwarded it to our Office where it was received on January 11, 1990. Since this correspondence was addressed to the contracting officer, and not to our Office, it was not effective for purposes of filing a protest with us. We advised McCullough by letter that we were treating its December 14 letter only as an information copy of an agency- level protest, and pointed out that any subsequent protest to the General Accounting Office must be filed within 10 days of formal notification of actual or constructive knowledge of initial adverse agency action. Bid Protest Regulations, 4 C.F.R. Sec. 21.2(a)(3) (1989).