[Decision Concerning Breach of Subcontract Claim]

B-226865 Jun 01, 1987
Jump To:
Skip to Highlights

Highlights

A firm filed a breach-of-subcontract claim, contending that the prime contractor improperly terminated a custodial services purchase order. GAO would not consider the claim, which involved a matter of contract administration not under its jurisdiction. Accordingly, the claim was dismissed.