Skip to main content

[Comments on Claims Court Case]

B-219706.2 Aug 18, 1986
Jump To:
Skip to Highlights

Highlights

BEFORE ACTION WAS TRIED. BOTH STIPULATION AND JUDGMENT WERE SILENT ON QUESTION OF INTEREST. CONTRACTOR'S ATTORNEY IS ADVISED THAT SINCE QUESTION OF ENTITLEMENT TO INTEREST STILL IN DISPUTE AND QUESTION RELATES TO CONTRACT WITH THE GOVERNMENT. IS FOR RESOLUTION UNDER CDA PROCEDURES. WHILE THE ACTION WAS PENDING. OR EMPLOYEES WITH RESPECT TO ITS CLAIM HEREIN NOR WILL IT CAUSE ANY SUCH ACTION TO BE FILED IN OR SUBMITTED TO ANY OTHER COURT. THERE WAS NO MENTION OF INTEREST IN EITHER THE STIPULATION OR THE JUDGMENT. THE JUDGMENT WAS PAID FOLLOWING THE USUAL PROCEDURES. 000 AND THE CHECK WAS SENT ON MARCH 11. OTHER AUTHORITIES. /2/ YOUR SUBMISSION INDICATES THAT FORTEC IS CLAIMING INTEREST UNDER SECTION 12 ONLY FROM THE DATE OF THE SETTLEMENT TO THE DATE OF PAYMENT.

View Decision

B-219706.2, AUG. 18, 1986, OFFICE OF THE GENERAL COUNSEL

GENERAL ACCOUNTING OFFICE - JURISDICTION - CONTRACTS - DISPUTES - CONTRACT DISPUTES ACT OF 1978 DIGEST: GOVERNMENT CONTRACTOR BROUGHT ACTION IN UNITED STATES CLAIMS COURT ON CONTRACT DISPUTES ACT (CDA) CLAIMS 41 U.S.C. SECS. 601-613. BEFORE ACTION WAS TRIED, UNITED STATES AND CONTRACTOR ENTERED INTO A WRITTEN AGREEMENT TO SETTLE CASE BY STIPULATING TO ENTRY OF JUDGMENT FOR $105,000. BOTH STIPULATION AND JUDGMENT WERE SILENT ON QUESTION OF INTEREST, ALTHOUGH STIPULATION INCLUDED BROAD RELEASE PROVISIONS. AFTER GOVERNMENT PAID JUDGMENT, CONTRACTOR DEMANDED GAO CERTIFY PAYMENT OF INTEREST UNDER 41 U.S.C. SEC. 611. DEPARTMENT OF JUSTICE OBJECTED TO INTEREST CERTIFICATION. CONTRACTOR'S ATTORNEY IS ADVISED THAT SINCE QUESTION OF ENTITLEMENT TO INTEREST STILL IN DISPUTE AND QUESTION RELATES TO CONTRACT WITH THE GOVERNMENT, PAYMENT CANNOT BE CERTIFIED, BUT IS FOR RESOLUTION UNDER CDA PROCEDURES.

DAVID W. MOCKBEE, ESQUIRE:

JONES, MOCKBEE, BASS & HODGE

1080 FLYNT DRIVE, SUITE E

JACKSON, MISSISSIPPI 39208

RE: CLAIM NO. Z-2854140(2), FORTEC CONSTRUCTORS, ET AL. V. THE UNITED STATES, IN THE UNITED STATES CLAIMS COURT; NO. 85-83C

THIS RESPONDS TO YOUR DEMAND FOR PAYMENT OF INTEREST ON THE JUDGMENT IN THE ABOVE-REFERENCED CASE. AS EXPLAINED BELOW, THIS OFFICE CURRENTLY CANNOT CERTIFY THE REQUESTED INTEREST PAYMENT BECAUSE A CONTROVERSY WHICH MAY BE LITIGATED STILL EXISTS BETWEEN THE UNITED STATES AND YOUR CLIENT REGARDING ITS ENTITLEMENT TO THE INTEREST CLAIMED.

THE JUDGMENT IN QUESTION RESOLVED CONTRACT DISPUTES ACT /1/ CLAIMS SUBMITTED BY FORTEC UNDER A CONSTRUCTION AND DEMOLITION CONTRACT IT HAD WITH THE COAST GUARD. WHILE THE ACTION WAS PENDING, THE PARTIES ENTERED INTO A WRITTEN AGREEMENT TO SETTLE THE MATTER BY STIPULATING TO THE ENTRY OF A JUDGMENT FOR THE PLAINTIFF IN THE AMOUNT OF $105,000. PARAGRAPH 4 OF THE STIPULATION STATES, "PLAINTIFF WAIVES AND ABANDONS ANY AND ALL CLAIMS AGAINST THE UNITED STATES, OR ITS OFFICERS, AGENTS, OR EMPLOYEES, ARISING OUT OF THE MATTERS AND FACTS INVOLVED IN THIS CASE." PARAGRAPH 8 SAYS:

"PLAINTIFF WARRANTS AND REPRESENTS THAT IT HAS PENDING NO OTHER ACTION OR SUIT AGAINST THE UNITED STATES OR ITS OFFICERS, AGENTS, OR EMPLOYEES WITH RESPECT TO ITS CLAIM HEREIN NOR WILL IT CAUSE ANY SUCH ACTION TO BE FILED IN OR SUBMITTED TO ANY OTHER COURT, ADMINISTRATIVE AGENCY, OR LEGISLATIVE BODY, INCLUDING BUT NOT LIMITED TO THE GENERAL ACCOUNTING OFFICE. ***"

PURSUANT TO THIS STIPULATION, THE CLAIMS COURT ENTERED ITS JUDGMENT, DATED OCTOBER 25, 1984, IN FAVOR OF FORTEC FOR THE AGREED AMOUNT. THERE WAS NO MENTION OF INTEREST IN EITHER THE STIPULATION OR THE JUDGMENT. THE JUDGMENT WAS PAID FOLLOWING THE USUAL PROCEDURES. WE ISSUED OUR SETTLEMENT CERTIFICATE ON MARCH 5, 1985, IN THE AMOUNT OF $105,000 AND THE CHECK WAS SENT ON MARCH 11.

SUBSEQUENTLY, BY LETTER DATED APRIL 9, 1985, YOU DEMANDED POST JUDGMENT INTEREST ON THE $105,000 CITING 31 U.S.C. SEC. 724(A) (NOW 31 U.S.C. SEC. 1304) AND 28 U.S.C. SEC. 2516(B). IN A SECOND LETTER, YOU AGAIN REQUESTED "POSTJUDGMENT" INTEREST BUT THIS TIME ON THE BASIS OF SECTION 12 OF THE CDA, 41 U.S.C. SEC. 611, AND OTHER AUTHORITIES. /2/ YOUR SUBMISSION INDICATES THAT FORTEC IS CLAIMING INTEREST UNDER SECTION 12 ONLY FROM THE DATE OF THE SETTLEMENT TO THE DATE OF PAYMENT.

FOLLOWING FORTEC'S INITIAL DEMAND, THE DEPARTMENT OF JUSTICE ADVISED THIS OFFICE THAT IT OBJECTED TO THE PAYMENT OF INTEREST IN THIS CASE. THE DEPARTMENT CONTENDED THAT FORTEC IS NOT ENTITLED TO INTEREST BECAUSE THE SETTLEMENT AGREEMENT ESTABLISHED AS A SUM CERTAIN THE AMOUNTS DUE WITH RESPECT TO THE ISSUES THEN IN DISPUTE BETWEEN THE PARTIES, AND SINCE THE AGREEMENT MADE NO PROVISION FOR THE PAYMENT OF INTEREST, NONE WAS OWING. FURTHER, THE DEPARTMENT MAINTAINED THAT THE SETTLEMENT AGREEMENT WAS BASED ON THE GOVERNMENT'S ABANDONMENT OF COUNTERCLAIMS AGAINST FORTEC, AND REPRESENTED THE RELEASE OF FUNDS WHICH THE GOVERNMENT HAD PREVIOUSLY WITHHELD UNDER THE CONTRACT, RATHER THAN PAYMENT ON ACCOUNT OF FORTEC'S CLAIM.

IN A LETTER SENT TO US IN RESPONSE TO THE DEPARTMENT'S ARGUMENTS, YOU DISPUTED THE POINTS THE DEPARTMENT RAISED. YOU MAINTAINED THAT THE SETTLEMENT AGREEMENT REPRESENTS A RESOLUTION OF THE DISPUTES SET FORTH IN THE COMPLAINT. YOU ASSERTED THAT THE COMPLAINT WAS NOT JUST FOR CONTRACT AMOUNTS WITHHELD BY THE GOVERNMENT, BUT ALSO FOR EXTRA WORK PERFORMED, ADDITIONAL COSTS INCURRED AND TIME EXTENSIONS. ALSO, CITING SEVERAL CONTRACT APPEALS BOARD DECISIONS, YOU ARGUED THAT THE FACT THAT THE DISPUTE WAS SETTLED DOES NOT PRECLUDE THE RECOVERY OF INTEREST. FINALLY, YOU ASSERTED THAT SINCE THE SETTLEMENT AGREEMENT AND JUDGMENT ARE SILENT WITH RESPECT TO INTEREST, INTEREST IS ALLOWABLE UNDER SECTION 12.

AS THE MATTER NOW STANDS, IT IS INAPPROPRIATE FOR THIS OFFICE TO TAKE ANY FURTHER ACTION. FORTEC'S CLAIM RAISES THE ISSUE OF THE APPLICATION OF SECTION 12 IN RELATION TO THE SPECIFIC RELEASE PROVISIONS OF THE SETTLEMENT AGREEMENT, A MATTER ON WHICH THE PARTIES APPEAR TO BE IN DISPUTE. FURTHER LITIGATION MAY BE NECESSARY TO RESOLVE THE MEANING AND EFFECT OF THE RELEASE PROVISIONS WITH RESPECT TO SECTION 12. SINCE THE DISPUTE STEMS FROM A GOVERNMENT CONTRACT, AND SINCE THE SETTLEMENT AGREEMENT RESULTED FROM LITIGATION BROUGHT UNDER THE CONTRACT DISPUTES ACT, WE THINK THE MATTER IS MORE APPROPRIATELY RESOLVED UNDER THE PROCEDURES PROVIDED IN THAT ACT. ACCORDINGLY, UNLESS AND UNTIL FORTEC'S ENTITLEMENT TO INTEREST IS DETERMINED IN ACCORDANCE WITH THE CDA, THERE IS NO BASIS FOR US TO CERTIFY ANY FURTHER PAYMENT.

Downloads

Office of Public Affairs