Please note that a lapse in appropriations has caused GAO to shut down its operations. Therefore, GAO will not be able to publish reports or otherwise update this website until GAO resumes operations. In addition, the vast majority of GAO personnel are not permitted to work. Consequently, calls or emails to agency personnel may not be returned until GAO resumes operations. For details on how the bid protest process will be handled during the shutdown, please see the legal decisions page. For information related to the GAO Personnel Appeals Board (PAB), please see the PAB webpage.

B-210135, JAN 10, 1983

B-210135 Jan 10, 1983
Jump To:
Skip to Highlights

Highlights

DIGEST: PROTEST AGAINST SOLICITATION SPECIFICATIONS RECEIVED BY GAO AFTER THE TIME SET FOR BID OPENING IS NOT TIMELY. BIDS WERE OPENED ON DECEMBER 9. OUR BID PROTEST PROCEDURES REQUIRE THAT A PROTEST BASED UPON ALLEGED IMPROPRIETIES IN A SOLICITATION WHICH ARE APPARENT PRIOR TO BID OPENING BE FILED PRIOR TO BID OPENING. 4 C.F.R. THE SPECIFICATIONS AND ANY OBJECTIONS THERETO WERE ASCERTAINABLE FROM READING THE SOLICITATION PRIOR TO BID OPENING. SINCE THE BASIS OF THE PROTEST WAS APPARENT BEFORE BID OPENING. IT IS UNTIMELY. THE PROTEST IS DISMISSED.

View Decision

B-210135, JAN 10, 1983

DIGEST: PROTEST AGAINST SOLICITATION SPECIFICATIONS RECEIVED BY GAO AFTER THE TIME SET FOR BID OPENING IS NOT TIMELY.

C.W.GIRARD, C.M.:

C.W.GIRARD, C.M. (GIRARD), PROTESTS AGAINST NO. JL USA-83-B-0001. BIDS WERE OPENED ON DECEMBER 9, 1982, AT 2 P.M. GAO RECEIVED THE PROTEST ON DECEMBER 10, 1982, AT 12:30 P.M.

OUR BID PROTEST PROCEDURES REQUIRE THAT A PROTEST BASED UPON ALLEGED IMPROPRIETIES IN A SOLICITATION WHICH ARE APPARENT PRIOR TO BID OPENING BE FILED PRIOR TO BID OPENING. 4 C.F.R. SEC. 21.2(B)(1). SEE CARRIER AIR CONDITIONING, B-208069, JULY 12, 1982, 82-2 CPD 46.

THE SPECIFICATIONS AND ANY OBJECTIONS THERETO WERE ASCERTAINABLE FROM READING THE SOLICITATION PRIOR TO BID OPENING. SINCE THE BASIS OF THE PROTEST WAS APPARENT BEFORE BID OPENING, BUT FILED AFTER BID OPENING, IT IS UNTIMELY.

ACCORDINGLY, THE PROTEST IS DISMISSED.

GAO Contacts

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries